Wind power is 70% useless in Ontario: economics report

23 Friday Jun 2017

Posted by Ottawa Wind Concerns in Renewable energy, Uncategorized, Wind power

≈ 3 Comments

Tags

cost of wind power, Counil for Clean and Reliable Energy, electricity bills Ontario, Green Energy Act, IESO, Marc Brouillette, renewable, Wind Concerns Ontario, wind farm, wind power Ontario, Wynne government

All that despoliation of Ontario communities, agricultural land and the natural environment for … what? Expensive power produced out of phase with demand, says Marc Brouillette

In a stunning commentary published yesterday by the Council for Clean and Reliable Energy, energy policy consultant Marc Brouilette says that Ontario’s wind power program is an expensive adventure that does not achieve any of its goals for the environment or economic prosperity, and is in fact, making things worse.

At a cost of $1.5 billion in 2015, Brouillette says, the fact that wind power generation is completely out of sync with demand in Ontario results in added costs for constrained generation form other sources. Constrained nuclear and hydro cost $300 million that year, and a further $200 million in costs was incurred due to “avoided” natural gas generation.

And, the power isn’t even getting to the people who need it. “[O]nly one-half of total provincial wind output makes it to the Central Region and the GTA where most of Ontario’s electricity demand exists,” Brouillette states.

All things considered, wind costs more than $410 per megawatt hour, which is four times the average cost of electricity in Ontario. This is being charged to Ontario’s electricity customers, at an increasing rate.

Ontario should reconsider its commitment to more wind, Brouillette concludes: “these challenges will increase if Ontario proceeds to double wind capacity to the projected ~6,500 MW.”

Reposted from Wind Concerns Ontario windconcernsontario.ca

Wind turbine noise reports not answered: Global News report

02 Friday Jun 2017

Posted by Ottawa Wind Concerns in Renewable energy, Wind power

≈ 3 Comments

Tags

Glen Murray MPP, Global News, MOECC, Shirlee Engel, Wind Concerns Ontario, wind farm, wind farm noise, wind turbines

Turbines surround a home in Huron County, Ontario. Complaints get no response. [Photo by Gary Moon]

The Global News investigative team took on the task of finding out what happens when people in rural Ontario report excessive noise and other effects from industrial-scale wind turbines in nearby wind power projects?
The answer, said Global National reporter Shirlee Engel is, “Not much.”
Here are Parts 1 and 2 of the Global News investigative report. The investigation took four months, and was based on documents and analysis provided to Global by Wind Concerns Ontario. It took two years for Wind Concerns to get the documents from the Ministry of the Environment and Climate Change (MOECC) under Freedom of Information legislation.
In over half the cases in the documents, the MOECC made no response; in others there was limited response. The Ministry relied upon wind power companies “predicted modeling” to determine whether noise exceedance was possible. When actual measurements of noise were done, they were limited to a narrow range of audible noise and did not include low frequency or tonal noise.
Minister Glen Murray told the Legislature yesterday after a barrage of questions from Opposition MPPs that the Ministry will now be including “tonal” noise in its measurement; the Minister still insists there is no problem, and told Global News that he has no complaints on his desk at present — Wind Concerns Ontario documents show almost 3,200 complaints filed between 2006 and 2014.

http://globalnews.ca/video/3498008/ontario-wind-turbine-complaints-fall-on-deaf-ears/
http://globalnews.ca/video/3498012/community-fed-up-with-ministrys-response-to-wind-turbine-complaints

Wind turbines not clean, not green

22 Monday May 2017

Posted by Ottawa Wind Concerns in Renewable energy, Wind power

≈ 1 Comment

Tags

clean energy, Matt Ridley, renewables, wind energry, wind farm, wind power, wind turbines

“The phrase ‘clean energy’ is a sick joke,” says Matt Ridley of the U.K. Here’s why.

The Global Wind Energy Council recently released its latest report, excitedly boasting that ‘the proliferation of wind energy into the global power market continues at a furious pace, after it was revealed that more than 54 gigawatts of clean renewable wind power was installed across the global market last year’.

You may have got the impression from announcements like that, and from the obligatory pictures of wind turbines in any BBC story or airport advert about energy, that wind power is making a big contribution to world energy today. You would be wrong. Its contribution is still, after decades — nay centuries — of development, trivial to the point of irrelevance.

Here’s a quiz; no conferring. To the nearest whole number, what percentage of the world’s energy consumption was supplied by wind power in 2014, the last year for which there are reliable figures? Was it 20 per cent, 10 per cent or 5 per cent? None of the above: it was 0 per cent. That is to say, to the nearest whole number, there is still no wind power on Earth.

Even put together, wind and photovoltaic solar are supplying less than 1 per cent of global energy demand. From the International Energy Agency’s 2016 Key Renewables Trends, we can see that wind provided 0.46 per cent of global energy consumption in 2014, and solar and tide combined provided 0.35 per cent. Remember this is total energy, not just electricity, which is less than a fifth of all final energy, the rest being the solid, gaseous, and liquid fuels that do the heavy lifting for heat, transport and industry.

Such numbers are not hard to find, but they don’t figure prominently in reports on energy derived from the unreliables lobby (solar and wind). Their trick is to hide behind the statement that close to 14 per cent of the world’s energy is renewable, with the implication that this is wind and solar. In fact the vast majority — three quarters — is biomass (mainly wood), and a very large part of that is ‘traditional biomass’; sticks and logs and dung burned by the poor in their homes to cook with. Those people need that energy, but they pay a big price in health problems caused by smoke inhalation.

Even in rich countries playing with subsidised wind and solar, a huge slug of their renewable energy comes from wood and hydro, the reliable renewables. Meanwhile, world energy demand has been growing at about 2 per cent a year for nearly 40 years. Between 2013 and 2014, again using International Energy Agency data, it grew by just under 2,000 terawatt-hours.

If wind turbines were to supply all of that growth but no more, how many would need to be built each year? The answer is nearly 350,000, since a two-megawatt turbine can produce about 0.005 terawatt-hours per annum. That’s one-and-a-half times as many as have been built in the world since governments started pouring consumer funds into this so-called industry in the early 2000s.

At a density of, very roughly, 50 acres per megawatt, typical for wind farms, that many turbines would require a land area greater than the British Isles, including Ireland. Every year. If we kept this up for 50 years, we would have covered every square mile of a land area the size of Russia with wind farms. Remember, this would be just to fulfil the new demand for energy, not to displace the vast existing supply of energy from fossil fuels, which currently supply 80 per cent of global energy needs.

Do not take refuge in the idea that wind turbines could become more efficient. There is a limit to how much energy you can extract from a moving fluid, the Betz limit, and wind turbines are already close to it. Their effectiveness (the load factor, to use the engineering term) is determined by the wind that is available, and that varies at its own sweet will from second to second, day to day, year to year.

As machines, wind turbines are pretty good already; the problem is the wind resource itself, and we cannot change that. It’s a fluctuating stream of low–density energy. Mankind stopped using it for mission-critical transport and mechanical power long ago, for sound reasons. It’s just not very good.

As for resource consumption and environmental impacts, the direct effects of wind turbines — killing birds and bats, sinking concrete foundations deep into wild lands — is bad enough. But out of sight and out of mind is the dirty pollution generated in Inner Mongolia by the mining of rare-earth metals for the magnets in the turbines. This generates toxic and radioactive waste on an epic scale, which is why the phrase ‘clean energy’ is such a sick joke and ministers should be ashamed every time it passes their lips.

It gets worse. Wind turbines, apart from the fibreglass blades, are made mostly of steel, with concrete bases. They need about 200 times as much material per unit of capacity as a modern combined cycle gas turbine. Steel is made with coal, not just to provide the heat for smelting ore, but to supply the carbon in the alloy. Cement is also often made using coal. The machinery of ‘clean’ renewables is the output of the fossil fuel economy, and largely the coal economy.

A two-megawatt wind turbine weighs about 250 tonnes, including the tower, nacelle, rotor and blades. Globally, it takes about half a tonne of coal to make a tonne of steel. Add another 25 tonnes of coal for making the cement and you’re talking 150 tonnes of coal per turbine. Now if we are to build 350,000 wind turbines a year (or a smaller number of bigger ones), just to keep up with increasing energy demand, that will require 50 million tonnes of coal a year. That’s about half the EU’s hard coal–mining output.

Forgive me if you have heard this before, but I have a commercial interest in coal. Now it appears that the black stuff also gives me a commercial interest in ‘clean’, green wind power.

The point of running through these numbers is to demonstrate that it is utterly futile, on a priori grounds, even to think that wind power can make any significant contribution to world energy supply, let alone to emissions reductions, without ruining the planet. As the late David MacKay pointed out years back, the arithmetic is against such unreliable renewables.

The truth is, if you want to power civilisation with fewer greenhouse gas emissions, then you should focus on shifting power generation, heat and transport to natural gas, the economically recoverable reserves of which — thanks to horizontal drilling and hydraulic fracturing — are much more abundant than we dreamed they ever could be. It is also the lowest-emitting of the fossil fuels, so the emissions intensity of our wealth creation can actually fall while our wealth continues to increase. Good.

And let’s put some of that burgeoning wealth in nuclear, fission and fusion, so that it can take over from gas in the second half of this century. That is an engineerable, clean future. Everything else is a political displacement activity, one that is actually counterproductive as a climate policy and, worst of all, shamefully robs the poor to make the rich even richer.

Spectator.co.uk/podcast
Matt Ridley discusses wind power

Read the whole article here

Ontario government not measuring wind turbine noise effectively, engineer tells international conference

22 Monday May 2017

Posted by Ottawa Wind Concerns in Health, Renewable energy, Wind power

≈ 1 Comment

Tags

environmental effects wind farms, MOECC, Ontario government, renewable energy, tonal noise wind turbines, William Palmer, wind farm, wind farm noise, wind turbine, Wind Turbine Noise 2017, Wynne government

Noise measurement protocol needlessly complex, failing to identify critical issues with wind turbine noise, Ontario engineer says.

He used MOECC data to confirm “tonal” quality to wind turbine noise emissions. One project has been operating for eight years — residents continue to complain, no action by Ontario government

Conference venue in Rotterdam: Wind Turbine Noise 2017

Ontario engineer William Palmer has proposed a rigorous, but simple and transparent technique to assess wind turbine noise, that could replace the problematic complex computer models and “black box” algorithms currently used in the Ontario Ministry of the Environment and Climate Change newest protocol to assess wind turbine noise compliance.

Speaking at the International Conference on Wind Turbine Noise that took place in Rotterdam beginning May 2, Palmer said of his proposed method,

The method had to consider that an effective monitoring system must take into account more than just averaging sound power levels over a long term. The method recognizes that humans are bothered by the changes and annoying characteristics that occur, as well as long term averages. Others describe this as the need to determine how the special characteristics of sound quality may impact quality of life.

To verify this approach, assessments were conducted using the method at two wind power developments in Ontario. In the K2 Wind project, he used MOECC data from testing in early March 2017 at a home within the K2 project. He was able to demonstrate that the MOECC data confirmed that the noise from the turbines surrounding the home had a tonal quality; that means it should require a 5 dB(A) penalty be applied to the other test results.

He reported:

Although the Ministry did not provide calibration files for their sound recordings they did provide in their report their assessment of the sound pressure level for each sample. Using the Electroacoustics Toolbox, and working backwards to set the given sound pressure level for a number of the recordings provided as the calibration level, permitted a “Quasi Calibration” of the Ministry data, and from that a calibrated FFT analysis was made. … Again, it was seen that when the residents described adverse effects in their comments filed with their initiation of recordings, FFT analysis of the sound recordings taken at those times clearly show a tonal condition occurring at about 450 Hz.

In the Enbridge project, where Mr. Palmer also conducted testing, he found similar tonal quality to the noise emissions in that project, and confirmed that the noise coming from the turbines is above the approved levels at several locations.

For this facility as an example, where the turbines first went into operation in November 2008, and citizen complaints occurred soon after, it has not yet been possible to complete a report to demonstrate compliance. The monitoring is still in progress, over 8 years later, with the turbines continuing in operation, and residents continuing to complain. The hypothesis is that individual samples are not representative due to variation.

Process is complex

He offered comment on the current protocol being used to assess compliance by the MOECC:

A premise of the Ministry of the Environment and Climate Change wind turbine monitoring protocol is that monitoring to show compliance must be conducted over a long period. The protocol requires the initial acoustic monitoring by residents to produce at least a 10-minute sample for each complaint period, and the final compliance protocol requires a minimum of 120 one-minute measurement intervals for each integer of wind speed. During each of those one-minute intervals there must be no changes in wind speed or direction. A further 60 samples are required for each integer wind speed with the turbines not operational. So far data collection has taken years to obtain a sufficient number of samples, and in at least one array, initial reports showed that over 90% of samples taken were discarded as non-compliant. All samples are logarithmically combined to determine the Leq produced by the facility, which eliminates any short-term change effects. This appears to be precisely the sort of monitoring that was cautioned against by Genuit and Fiebig described in Section 1 when they noted, “By relying on sound pressure levels averaged over long time periods and suppressing all aspects of quality, the specific properties of environmental noise situations cannot be identified, because annoyance caused by environmental noise has a broader linkage with various acoustical properties such as frequency spectrum, duration, impulsive, tonal and low-frequency components, etc. than only with SPL [Sound Pressure Level]. In many cases these acoustical properties affect the quality of life.”

The annoyance aspects that impact the quality of life of impacted residents are not being assessed.

People walking away from loved homes

The current protocol cannot possibly identify critical issues in wind turbine noise emissions, Palmer asserts. In conclusion, he said:

This paper has demonstrated a method for rigorous monitoring of wind turbine sound. The goal of the method was to establish evidence for the condition noted by Karl D. Kryter: “The most direct, and perhaps most valid, insight into the possible presence and magnitude of stress reactions in general living environments is probably that which has been obtained from attitude surveys and real-life behaviour of people.” Behaviours such as walking away from an unsold loved home to live at the home of a family member, or when normal people become activists in trying to communicate their concerns provide such valid insights. The rigorous method had to consider the present acceptance criterion for wind turbines, in light of the insight given by those who study the quality of noise and its relation to annoyance. Those who study the subject identify that, “Current acceptance criterion relying on sound pressure levels averaged over long time periods and suppressing all aspects of quality cannot identify the specific properties of environmental noise situations.”

The results reported by Bill Palmer are typical of the community testing being undertaken in many communities near wind turbine projects across Ontario.

These findings indicate that the complex processes used by the MOECC and required of wind companies for compliance testing fail to identify key issues that can be quickly identified using much simpler techniques.

Meanwhile, the turbines, shown by other methods to be out of compliance, continue to operate.

[Re-posted from Wind Concerns Ontario]

Endangered turtles win wind farm appeal in Prince Edward County

27 Thursday Apr 2017

Posted by Ottawa Wind Concerns in Renewable energy, Wind power

≈ Leave a comment

Tags

APPEC, community opposition wind farm, endangered species Ontario, environmental damage wind farm, prince Edward County, Wind Concerns Ontario, wind energy, wind farm, wind farm legal action, wind power, wind turbines

ENDANGERED TURTLES WIN PROTECTION FROM WIND FARM IN ONTARIO, CANADA

The Environmental Review Tribunal determined the Blandings Turtle was endangered by the wind farm

Landmark legal decision overturns government approval of large power project

WELLINGTON, ONTARIO, CANADA, April 27, 2017 /EINPresswire.com/ —
A years-long legal battle over a wind power project by Germany-based wpd in Ontario, Canada, resulted in a ruling by the provincial government’s Environmental Review Tribunal yesterday, in favour of protecting an endangered species of turtle.

In the Tribunal ruling, government approval for 18 of 29 industrial-scale wind turbines in the “White Pines” project was reversed. With 60 percent of the project removed, it may be impossible for the power developer to meet its contractual obligation.

The citizens of Prince Edward County, about two hours east of Toronto, where the project was to be located, fought the wind turbines for almost 10 years, and spent almost $2 million CAD in legal fees.

“The County” as it is called, on the shores of Lake Ontario, is a stopping place for hundreds of thousands of birds migrating in eastern North America, and was identified as an Important Bird Area by conservation groups. The area is also a habitat for the endangered Blandings turtle, and home to the Little Brown Bat which is on the verge of extirpation.

“This [decision] is clearly a victory for the survival of the Blanding’s turtle and many other animal and plant species,” said Alliance to Protect Prince Edward County president Gordon Gibbins. “Although the Tribunal decision was specifically concerned with protecting the turtles and their habitat, we are very pleased that indirectly as a result of this decision there will be no turbines in the Prince Edward County Important Bird and Biodiversity Area.”

“The Tribunal decision has made it clear that this wind power project was never about protecting the environment,” said Jane Wilson, president of Wind Concerns Ontario, the coalition of community groups concerned about wind power projects.

“The wind power project was always about money. The citizens of Prince Edward County fought hard to protect the environment and wildlife against our own Ministry of the Environment.”

Citizen evidence was crucial in bringing forward evidence of harm to the environment in the various appeals of the power project, Wilson says. “The government did little or no oversight on how wildlife is to be protected, and it was the people of Prince Edward County who brought the information to the Tribunal. As a result, in Ontario now, wind power does not automatically override environmental concerns.”

Economic impacts were also a concern for the community. The County is a tourist destination with dozens of wineries and cheese establishments; winery owners were concerned about the negative impact of the huge power-generating turbines on the County with its quaint villages and pastoral views as a tourist attraction.

Prince Edward County Mayor Robert Quaiff said, “Our community has been fighting this project for quite some time. I’m glad to see that the Environmental Review Tribunal has recognized and given credence to our concerns.”

For more information, visit Wind Concerns Ontario at www.windconcernsontario.ca
905-362-9334

Jane Wilson
Wind Concerns Ontario
905-362-9334
email us here

New wind turbine noise guidelines fail to address problems

26 Wednesday Apr 2017

Posted by Ottawa Wind Concerns in Health, Renewable energy, Wind power

≈ 1 Comment

Tags

community opposition wind farm, Glen Murray, infrasound wind turbines, low frequency noise, MOECC, Ontario, Ontario Ministry of the Environment and Climate Change, renewable energy, tonal noise wind turbines, wind farm, wind farm noise, wind farm siting, wind mill, wind power, wind turbine, wind turbine noise

New Ontario wind turbine noise compliance protocol falls short

Way short.

As in, little or no understanding of the problems with wind turbine noise emissions.

New noise protocol misses all the problems

 

On Friday, April 21, the Ministry of the Environment and Climate Change released a new protocol document intended for “assessing noise from wind turbines that have already been built. It is used by industry and ministry staff to monitor compliance.”

While in the absence of guidance for staff, and the complete lack of compliance audit information from wind power developers and operators, this is a step forward, the truth is, the protocol doesn’t change much.

Here’s why:

  • the protocol still relies on audible noise only, when many of the complaints registered with the MOECC concern effects that are clearly linked to other forms of noise
  • the protocol does not take into account lower wind speeds, which is where problems are being experienced, particularly with newer, more powerful turbines
  • there is no comment on any sort of transition between the protocol that existed before and this one

Improvements:

  • the Ministry’s action in producing this protocol is an indication that they know they have a problem
  • the description of Ministry response is a good step forward
  • requiring wind power companies to actually have, and to publish, compliance audit documents could be a sign of expectations of greater accountability among the power developers/wind power project operators.

This table outlines the critical gaps in the new protocol document.

 

Issue     Protocol Requirements Actual Experiences
Wind Speeds Assessment of noise at wind speeds between 4 m/s and 7 m/s MOECC testing indicates problem noise starts below 3 m/s which is outside of wind speeds involved in the protocol.
Ambient Noise Narrow time period assessed Wide seasonal variations while wind turbine noise constant
Location Only test outside of home Very different inside noise conditions
Tonal Assessments Uses criticized techniques Narrow band analysis shows tonal noise present.
Resident Input None Resident concerns drive other MOECC procedures
Frequencies Excludes Infrasound Elevated levels of infrasound in homes

 The Ministry of the Environment and Climate Change needs to acknowledge that there is a problem with wind turbine noise, and accept that it must play a role as a government agency charged with protecting the environment and people in it — preparing an industry-led document may look like a positive step, but this document does not meet the needs of the people of Ontario forced to live with wind turbines, and their noise emissions.

Wind Concerns Ontario

Wind power developer uses threat to influence environmental agency

15 Saturday Apr 2017

Posted by Ottawa Wind Concerns in Renewable energy, Wind power

≈ 9 Comments

Tags

Alliance to protect Prince Edward County, APPEC, Blanding's Turtle, Environmental Review Tribunal, Ontario Ministry of the Environment and Climate Change, prince Edward County, wind farm, wind fram environmental damage, wind power, wind turbines

Power developer announcement it is about to clear land which is habitat for an endangered species is an attempt to force the Environmental Review Tribunal to issue a decision on the Prince Edward County wind power project, and proposed “remedies” for species at risk

The Environmental Review Tribunal determined the Blandings Turtle was endangered by the wind farm; the company is proceeding with construction in the absence of a final decision

April 15, 2017

Minutes before 4 PM on the Thursday of the Easter weekend, Germany-based wind power developer WPD issued notice to the Environmental Review Tribunal that the company intends to start clearing land in advance of building the White Pines power project.

Land clearing is to begin on Wednesday, the corporate power developer said, which meant there is only one day after the Easter weekend to file any documents against the action.

The White Pines project has been contested in an appeal before the Tribunal; the original decision found that the power project would cause harm to endangered species of turtles and bats. A hearing was held in late January to hear possible “remedy” actions to prevent loss of life, but a decision accepting or rejecting the remedies has not yet been rendered.

WPD is in danger of being in breach of its contract with the Ontario government if it does not begin supplying power by the critical Commercial Operation Date.

The Blandings Turtle, one of the endangered species at risk from the wind power project construction, has already been seen in the County by residents, so has emerged from hibernation.

The rush to construction shows how willing the wind power developer is to risk environmental damage, a spokesperson for the Alliance to Protect Prince Edward County told news media Quinte News.

At an earlier phase of the White Pines project WPD began unauthorized land clearing but was halted by an order from the Environmental Review Tribunal. WPD is also the power developer behind the contentious Fairview Wind project near Collingwood. It threatened to sue the Ontario government if a contract was not issued for the power project.

Previous attempt by WPD to clear land for unauthorized construction of the Prince Edward County wind power project

 

 

Prince Edward County in state of emergency following pollution incident

29 Wednesday Mar 2017

Posted by Ottawa Wind Concerns in Health, Renewable energy, Wind power

≈ 2 Comments

Tags

Amherst Island, Picton, prince Edward County, wind farm, wind farm environmental damage, wind farm marine safety, wind farm pollution, wind power

 

Barge carrying construction equipment and material: no plan in place at the time of accident [Photo Jay Pickerel/Facebook]

A barge carrying construction materials to the Windlectric wind farm site on nearby Amherst Island sank this past weekend, polluting Picton Bay with diesel fuel. The bay is the source of drinking water for Picton; at the time of the incident, the wind power company had not yet filed a mandatory Marine Logistic Plan to document safety measures.

The Amherst Island group says in light of violations of terms of the power developer’s agreement with the government, the project –which will cost Ontario electricity customers $500 million over 20 years–should be cancelled.

A news story from CTV is here:

http://www.ctvnews.ca/canada/picton-water-treatment-plant-reopens-but-water-emergency-remains-in-place-1.3345517

The Association to Protect Amherst Island issued this statement today.

Dear Premier Wynne

Prince Edward County Mayor Robert Quaiff has declared a water emergency as a result of contaminants approaching the Picton-Bloomfield water intake due to a partially sunken barge in Picton Harbour under contract to McNeil Marine and ultimately under contract to Algonquin Power/Windlectric for the proposed Amherst Island Wind Project.
The silence from Algonquin Power/Windlectric is deafening.
Indeed Algonquin/Windlectric had the audacity to attempt to continue aggregate delivery from Picton Terminals to Amherst Island yesterday (Tuesday March 28 2017) but was thwarted either because either the water was too low or the dock too high, yet another example of the comedy of errors associated with this ill-conceived project.
The Association to Protect Amherst Island reiterates its request for MOECC to issue an immediate stop work order for the Amherst Island Wind Project until such time as a comprehensive report is available for the Picton Harbour incident and a preventative action plan is is place to address the high risk to public and environmental safety of all aspects of the project. and to address the need for a Major Design Modification to address the changed project location to include Picton Terminals.
 
At the same time, the Association reaffirms its request to reject the proposed amendment to the Certificate of Property Use for the contaminated  Invista Lands on Bath Road (EBR 012-9749) designated as parkland.  Similar to the Picton Harbour situation, a water intake exists in proximity to the proposed mainland dock for the Amherst Island Wind Project and serves a local industrial park.  Algonquin/Windlectric in its Marine Safety Plan now advises that fuelling of barges is proposed at the mainland dock location.  Not only is the land contaminated with the possibility of pollution of Lake Ontario, the company plans to fuel in proximity to a water intake.

The same “Marine Safety Plan” fails to address any aspect of transport of materials from Picton terminals except for a vague reference that “The bulk barge and the ATV (Aggregate Transfer Vessel)  will approach and leave the island dock area from the west, . . . ” as if from the Land of Oz.  The Association is in the process of reviewing this “too little, too late” document and will have further comments about use of barges in ice conditions, the lack of traffic volume, lack of simulation of barges crossing the ferry path, incomplete information about the installation of the high voltage transmission line from the mainland to the Island and the total lack of risk assessment, failure to mention Picton Terminals,among other matters.

The use of an “Aggregate Transfer Vessel” was not identified in the REA submission and no stockpiling of aggregate was proposed other than in immediate proximity to the proposed cement batching plant by the Island school.
The Association has emphasized the importance of marine safety since this project was proposed and has pleaded with politicians, MOECC, Ontario’s Chief Drinking Water Official and the Chief Fire Marshall and Head of Emergency Preparedness.
Please take immediate action to stop the Amherst Island Wind Project before a tragedy occurs.
Thank you.
Sincerely
Michèle Le Lay
President
Association to Protect Amherst Island
protectai@kos.net

Site plan for North Stormont wind power project shows 34 turbines planned

22 Wednesday Mar 2017

Posted by Ottawa Wind Concerns in Renewable energy, Wind power

≈ 1 Comment

Tags

Concerned Citizens of North Stormont, EDP Renewables, Finch Ontario, Glenn Thibeault, hydro bills Ontario, IESO, North Stormont, power Ontario, Wind Concerns Ontario, wind energy, wind farm, wind power, wind turbines

The 100-megawatt project will cost more than $400 million, while Ontario already has a surplus of power

EDP Renewables, headquartered in Madrid, has posted the site plan for its 100-megawatt “Nation Rise” wind power project, in North Stormont, about 40 minutes south and east of Ottawa.

Details posted:

Project Name: Nation Rise Wind Farm

IESO Reference Number: L-006351-WIN-001-100

Project Location: The proposed Nation Rise Wind Farm will be located on private and public lands in the United Counties of Stormont, Dundas and Glengarry in the western portion of the Township of North Stormont, Ontario, and bounded to the south by the Township of South Stormont and to the west by the boundary of the Township of North Dundas. The north portion of the site is delimited by the municipality boundaries of Russell and the Nation. Courville Road and MacMillan Road are the east boundaries of the project.

Dated at: the Township of North Stormont this 17th day of March 2017.

Other project documents including the draft noise impact assessment are available on the Nation Rise wind “farm” website here.

Residents interested in learning more about the impact of the power project on the area’s homes, environment and wildlife, and in supporting the group’s activities and legal fund, should contact the Concerned Citizens of North Stormont*, whose website is here.

The 20-year contract with the Independent Electricity System Operator (IESO) will cost Ontario electricity ratepayers about $436 million.

The Minister of Energy, Glenn Thibeault, has stated, meanwhile, that Ontario currently has a surplus of power (which is being sold off at prices below what power developers are paid). The Nation Rise contract could be cancelled under a pre-construction liability clause for $600,000, according to IESO documents.

Minister Thibeault told a business audience in Toronto last year that the government’s “arbitrary” selection of wind power led to “sub-optimal siting” and “heightened community concerns.”

North Stormont is a Not A Willing Host community.

Concerned Citizens of North Stormont leader Margaret Benke, at a recent information event in Finch, Ontario

*Concerned Citizens of North Stormont is a chapter of Wind Concerns Ontario, as is Ottawa Wind Concerns.

Wind power contracts add to rising hydro bills, says Ottawa Wind Concerns

25 Saturday Feb 2017

Posted by Ottawa Wind Concerns in Ottawa, Renewable energy, Wind power

≈ 4 Comments

Tags

hydro bills Ontario, Lisa MacLeod MPP, North Gower, Ontario, Ottawa wind concerns, Parker Gallant, PCPO, Scott Moffatt Rideau-Goulbourn, surplus power Ontario, wind energy, wind farm, wind power

February 25, 2017

Wind power contracts should be cancelled: Mike Baggott of Ottawa Wind Concerns

Wind power contracts should be cancelled to control electricity costs: Mike Baggott of Ottawa Wind Concerns

Ottawa Wind Concerns was an invited guest speaker this week at a pre-budget consultation event held by Nepean-Carleton MPP Lisa MacLeod, at the Alfred Taylor Centre in North Gower.

Executive member with the group and North Gower resident Mike Baggott told the audience that while Ontario’s electricity bills are among the highest in North America, more costs, specifically expensive wind power contracts awarded to power developers, were yet to come.

“Everyone wants to do the right thing for the environment,” Baggott explained, “but has the Ontario government done the right thing?” Two Auditors General said there was never any cost-benefit or impact analysis for the province’s green energy plan, and the Wynne government pays twice as much for renewable energy as other jurisdictions do. The expensive wind contracts are among the factors pushing electricity bills up.

“As high as our bills are now,” Baggott said, “they will get worse if projects in Ontario recently awarded contracts are allowed to proceed.”

He noted the power projects in La Nation, east of Ottawa, and North Stormont –both opposed by the local communities — will cost Ontario ratepayers over $600 million for the 20-year contracts.

In all, Ontario is facing $5 billion in new wind power contracts, at a time when the province has a surplus of power. Wind power also cannot demonstrate any benefits to the environment, Baggott said.

“It’s time to stop digging the hole,” Baggott concluded.

The main speaker at the event was Parker Gallant, a former banker whose energy sector analysis is frequently published in The Financial Post, who explained line by line, “What’s in Your Hydro Bill.”

MPP MacLeod outlined steps that can be taken to control electricity costs, and answered questions from the audience.

“It’s hard not to get depressed when you hear, line by line, how we got here with our electricity bills,” commented Rideau-Goulbourn councilor Scott Moffatt.

Parker Gallant: what's in your hydro bill? A lot of government mistakes

Parker Gallant: what’s in your hydro bill? A lot of government mistakes

 

← Older posts
Newer posts →

Recent Posts

  • Land use conflict prompts citizen legal action over West Carleton battery storage site
  • Energy Minister Stephen Lecce speaks out on renewable power sources wind and solar; emphasizes cost, reliability
  • Open letter to CAFES Ottawa
  • Ottawa Wind Concerns supports West Carleton residents
  • What does wind ‘farm’ construction really look like?

Follow me on Twitter

My Tweets

Enter your email address to follow this blog and receive notifications of new posts by email.

Tags

Bob Chiarelli Green Energy Act IESO Ontario Ottawa Ottawa wind concerns wind energy wind farm wind power wind turbines

Contact us

PO Box 3 North Gower ON K0A 2T0

Create a free website or blog at WordPress.com.

Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Subscribe Subscribed
    • Ottawa Wind Concerns
    • Join 379 other subscribers
    • Already have a WordPress.com account? Log in now.
    • Ottawa Wind Concerns
    • Subscribe Subscribed
    • Sign up
    • Log in
    • Report this content
    • View site in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...