Power developer announcement it is about to clear land which is habitat for an endangered species is an attempt to force the Environmental Review Tribunal to issue a decision on the Prince Edward County wind power project, and proposed “remedies” for species at risk

The Environmental Review Tribunal determined the Blandings Turtle was endangered by the wind farm; the company is proceeding with construction in the absence of a final decision
April 15, 2017
Minutes before 4 PM on the Thursday of the Easter weekend, Germany-based wind power developer WPD issued notice to the Environmental Review Tribunal that the company intends to start clearing land in advance of building the White Pines power project.
Land clearing is to begin on Wednesday, the corporate power developer said, which meant there is only one day after the Easter weekend to file any documents against the action.
The White Pines project has been contested in an appeal before the Tribunal; the original decision found that the power project would cause harm to endangered species of turtles and bats. A hearing was held in late January to hear possible “remedy” actions to prevent loss of life, but a decision accepting or rejecting the remedies has not yet been rendered.
WPD is in danger of being in breach of its contract with the Ontario government if it does not begin supplying power by the critical Commercial Operation Date.
The Blandings Turtle, one of the endangered species at risk from the wind power project construction, has already been seen in the County by residents, so has emerged from hibernation.
The rush to construction shows how willing the wind power developer is to risk environmental damage, a spokesperson for the Alliance to Protect Prince Edward County told news media Quinte News.
At an earlier phase of the White Pines project WPD began unauthorized land clearing but was halted by an order from the Environmental Review Tribunal. WPD is also the power developer behind the contentious Fairview Wind project near Collingwood. It threatened to sue the Ontario government if a contract was not issued for the power project.

Previous attempt by WPD to clear land for unauthorized construction of the Prince Edward County wind power project
Pingback: White Pines wind power developer notifies intentions for vegetation clearing | Alliance to Protect Prince Edward County
Reblogged this on ajmarciniak.
Pingback: They Stoop to Intimidate | WAINFLEET WIND ACTION GROUP
In Huron County people who had done the research and realized how ill informed residents were of the potential for harm from the turbines and their infrastructure, tried every possible way they could think of to prevent wind companies from going forward. Even bringing in one of the best lawyers in the country to challenge the incursion, as a human rights violation, was unsuccessful. The judge said that because the turbines and substation had not been started yet, there could be no court decision to stop the wind company from proceeding.
I sure hope the folks in Prince Edward County and on Amherst Island will use civil disobedience to prevent the ruination of their communities. This government has given people no other options.
Please correct me if I’m wrong.
Civil disobedience is not the answer. The Drennan case to which you refer did proceed and was heard in January; a decision was rendered a few weeks ago, it is worth a read.
Reblogged this on How Green Is This.
Why are we not hearing any updates on this situation?
The ERT asked for all submissions to be made in writing; it is now one week since WPD began clearing vegetation for turbine access roads, without a Notice To Proceed, and without a final decision from the Environmental Review Tribunal.