Barge carrying construction equipment and material: no plan in place at the time of accident [Photo Jay Pickerel/Facebook]
A barge carrying construction materials to the Windlectric wind farm site on nearby Amherst Island sank this past weekend, polluting Picton Bay with diesel fuel. The bay is the source of drinking water for Picton; at the time of the incident, the wind power company had not yet filed a mandatory Marine Logistic Plan to document safety measures.
The Amherst Island group says in light of violations of terms of the power developer’s agreement with the government, the project –which will cost Ontario electricity customers $500 million over 20 years–should be cancelled.
The Association to Protect Amherst Island issued this statement today.
Dear Premier Wynne
Prince Edward County Mayor Robert Quaiff has declared a water emergency as a result of contaminants approaching the Picton-Bloomfield water intake due to a partially sunken barge in Picton Harbour under contract to McNeil Marine and ultimately under contract to Algonquin Power/Windlectric for the proposed Amherst Island Wind Project.
The silence from Algonquin Power/Windlectric is deafening.
Indeed Algonquin/Windlectric had the audacity to attempt to continue aggregate delivery from Picton Terminals to Amherst Island yesterday (Tuesday March 28 2017) but was thwarted either because either the water was too low or the dock too high, yet another example of the comedy of errors associated with this ill-conceived project.
The Association to Protect Amherst Island reiterates its request for MOECC to issue an immediate stop work order for the Amherst Island Wind Project until such time as a comprehensive report is available for the Picton Harbour incident and a preventative action plan is is place to address the high risk to public and environmental safety of all aspects of the project. and to address the need for a Major Design Modification to address the changed project location to include Picton Terminals.
At the same time, the Association reaffirms its request to reject the proposed amendment to the Certificate of Property Use for the contaminated Invista Lands on Bath Road (EBR 012-9749) designated as parkland. Similar to the Picton Harbour situation, a water intake exists in proximity to the proposed mainland dock for the Amherst Island Wind Project and serves a local industrial park. Algonquin/Windlectric in its Marine Safety Plan now advises that fuelling of barges is proposed at the mainland dock location. Not only is the land contaminated with the possibility of pollution of Lake Ontario, the company plans to fuel in proximity to a water intake.
The same “Marine Safety Plan” fails to address any aspect of transport of materials from Picton terminals except for a vague reference that “The bulk barge and the ATV (Aggregate Transfer Vessel) will approach and leave the island dock area from the west, . . . ” as if from the Land of Oz. The Association is in the process of reviewing this “too little, too late” document and will have further comments about use of barges in ice conditions, the lack of traffic volume, lack of simulation of barges crossing the ferry path, incomplete information about the installation of the high voltage transmission line from the mainland to the Island and the total lack of risk assessment, failure to mention Picton Terminals,among other matters.
The use of an “Aggregate Transfer Vessel” was not identified in the REA submission and no stockpiling of aggregate was proposed other than in immediate proximity to the proposed cement batching plant by the Island school.
The Association has emphasized the importance of marine safety since this project was proposed and has pleaded with politicians, MOECC, Ontario’s Chief Drinking Water Official and the Chief Fire Marshall and Head of Emergency Preparedness.
Please take immediate action to stop the Amherst Island Wind Project before a tragedy occurs.
The 100-megawatt project will cost more than $400 million, while Ontario already has a surplus of power
EDP Renewables, headquartered in Madrid, has posted the site plan for its 100-megawatt “Nation Rise” wind power project, in North Stormont, about 40 minutes south and east of Ottawa.
Details posted:
Project Name: Nation Rise Wind Farm
IESO Reference Number: L-006351-WIN-001-100
Project Location: The proposed Nation Rise Wind Farm will be located on private and public lands in the United Counties of Stormont, Dundas and Glengarry in the western portion of the Township of North Stormont, Ontario, and bounded to the south by the Township of South Stormont and to the west by the boundary of the Township of North Dundas. The north portion of the site is delimited by the municipality boundaries of Russell and the Nation. Courville Road and MacMillan Road are the east boundaries of the project.
Dated at: the Township of North Stormont this 17th day of March 2017.
Other project documents including the draft noise impact assessment are available on the Nation Rise wind “farm” website here.
Residents interested in learning more about the impact of the power project on the area’s homes, environment and wildlife, and in supporting the group’s activities and legal fund, should contact the Concerned Citizens of North Stormont*, whose website is here.
The 20-year contract with the Independent Electricity System Operator (IESO) will cost Ontario electricity ratepayers about $436 million.
The Minister of Energy, Glenn Thibeault, has stated, meanwhile, that Ontario currently has a surplus of power (which is being sold off at prices below what power developers are paid). The Nation Rise contract could be cancelled under a pre-construction liability clause for $600,000, according to IESO documents.
Minister Thibeault told a business audience in Toronto last year that the government’s “arbitrary” selection of wind power led to “sub-optimal siting” and “heightened community concerns.”
North Stormont is a Not A Willing Host community.
Concerned Citizens of North Stormont leader Margaret Benke, at a recent information event in Finch, Ontario
*Concerned Citizens of North Stormont is a chapter of Wind Concerns Ontario, as is Ottawa Wind Concerns.
Wind power contracts should be cancelled to control electricity costs: Mike Baggott of Ottawa Wind Concerns
Ottawa Wind Concerns was an invited guest speaker this week at a pre-budget consultation event held by Nepean-Carleton MPP Lisa MacLeod, at the Alfred Taylor Centre in North Gower.
Executive member with the group and North Gower resident Mike Baggott told the audience that while Ontario’s electricity bills are among the highest in North America, more costs, specifically expensive wind power contracts awarded to power developers, were yet to come.
“Everyone wants to do the right thing for the environment,” Baggott explained, “but has the Ontario government done the right thing?” Two Auditors General said there was never any cost-benefit or impact analysis for the province’s green energy plan, and the Wynne government pays twice as much for renewable energy as other jurisdictions do. The expensive wind contracts are among the factors pushing electricity bills up.
“As high as our bills are now,” Baggott said, “they will get worse if projects in Ontario recently awarded contracts are allowed to proceed.”
He noted the power projects in La Nation, east of Ottawa, and North Stormont –both opposed by the local communities — will cost Ontario ratepayers over $600 million for the 20-year contracts.
In all, Ontario is facing $5 billion in new wind power contracts, at a time when the province has a surplus of power. Wind power also cannot demonstrate any benefits to the environment, Baggott said.
“It’s time to stop digging the hole,” Baggott concluded.
The main speaker at the event was Parker Gallant, a former banker whose energy sector analysis is frequently published in The Financial Post, who explained line by line, “What’s in Your Hydro Bill.”
MPP MacLeod outlined steps that can be taken to control electricity costs, and answered questions from the audience.
“It’s hard not to get depressed when you hear, line by line, how we got here with our electricity bills,” commented Rideau-Goulbourn councilor Scott Moffatt.
Parker Gallant: what’s in your hydro bill? A lot of government mistakes
EDP wind turbine and home at South Branch project, Brinston, Ontario. Photo by Ray Pilon.
October 21, 2016
Portugal-based power developer EDP Renewables is holding an Open House for its Nation Rise wind power project on Tuesday, October 25, from 4-8 PM in Finch Ontario, at the Finch arena.
The 100-megawatt power project is located completely in the Township of North Stormont; it was one of five to receive a contract from the Independent Electricity System Operator (IESO) earlier this year, and one of three projects to win a contract despite being proposed in an unwilling host community.
The contract is worth $436 million over 20 years.
In September, the IESO announced that Ontario has a surplus of power and that the new contract process scheduled for 2017 is now suspended. The IESO did not announce plans to cancel any of the contracts for more unneeded wind power announced a few months previous, despite IESO representative statements that the contracts are contributing to Ontario’s electricity bills.
Citizens of the area have formed a community group Concerned Citizens of North Stormont, and vowed to fight approval of the project, including legal action in future if necessary.
People gather at EDP Renewables open house in August, 2015
Wind turbines may close busy airport: pilots launch political campaign
This is an excerpt from the August edition of COPA Flight, provided by a member of the Canadian Owners and Pilots Association.
So ridiculous, pilots can’t believe anyone would put turbines at an airport
Windmills may close airport
By Russ Niles
The owner of an Ontario airport that will be in the shadow of a proposed wind turbine project fears Transport Canada [TC] will close his strip if the windmills are built.
Kevin Elwood says he’s been told by a senior TC official that the department will not intervene to prevent construction of the windmills but it will act to ensure public safety after the fact by restricting or even stopping operations at the affected airport.
“He said that if [the province of Ontario] chooses to put green energy before airports, that’s their choice,” he said. “We will respond by restricting airport operations and we will go so far as to close airports,” he {Elwood] quoted the official as saying.
That would seem to fit with the scenario now playing out over the so-called Fairview Project, a group of eight, 152-metre turbines planned for farmland adjacent to Elwood’s Clearview Aerodrome (also known as Stayner Airport). The huge windmills will be directly in the flightpath of aircraft in the circuit for his airport and the nearby Collingwood Airport.
TC has declined to oppose the project and that means the only hope Elwood and other opponents of the windmills have is the rarely used power on the Minister of Transport to unilaterally stop the project on safety grounds.
Minister Marc Garneau has so far been silent on the issue and COPA is calling on its 17,000 members (and voters) to apply their significant political influence to nudge him out of that complacency.
COPA has launched a full-scale letter writing campaign to draw attention to the issue that Elwood is convinced is an immediate threat to both airports and will set a precedent that could affect airports across the country.
The turbines would be in blatant violation of Transport Canada’s airport obstacle guidelines and Garneau, a long-time pilot and COPA member, has the power to stop their construction. In fact, because of the protection afforded such projects by Ontario’s Green Energy Act, Garneau is probably one of the few who can stop them. He won’t even talk about the issue, however.
“We really have a good working relationship with Transport Canada, very open and collaborative,” [says COPA President Bernard Gervais]. “As part of our regular discussions I presented the situation and possible course of action,” Gervais said. “Section 6.41 of the Aeronautics Act authorizes the minister to make an interim order to deal with such threats to aviation. If the minister is of the opinion that the windmills are hazardous to aviation safety, he (or his deputy) has the authority to stop such construction. … the lack of feedback from TC and knowing this is a very sensitive political issue, drives me to think that our only course of action at this point is to go on the political front.”
ERT members unfamiliar with aviation safety
COPA appeared at the original [ERT] hearings in the approval* process along with many other opponents, and all of the arguments were essentially ignored. … Complicating that process is the fact that the two members hearing the health arguments have no aviation background at all and have had to be schooled on airport operations and aviation terminology.
… [Elwood] says that if it plays out as he thinks it might, TC will either close his airport or make it so difficult and inconvenient to use that it might as well be closed. The aerodrome is home bas to Elwood’s business, an aircraft management and business charter operation. Over the years he’s invested heavily in hangars and other infrastructure and if the windmills go ahead, a lifetime of work might go down the drain.
[The wind turbines] will prevent pilots from using the recently re-invigorated [Collingwood Airport]. Ironically, the federal government has spent millions on improvements to the field, including a new terminal and lots of new pavement.
“Even people who don’t fly, [says Collingwood based pilot Austin Boake], they realize it’s just common sense …It’s just so ridiculous I can’t even believe it.”
Wind turbines near SS Marie: power supply saturated but Ontario buying more wind. (National Post photo)
Worthy of a repost, from the National Post, this opinion from a renewable energy insider.
September 2, 2016
Ontario set an all-time peak electricity demand of 27,005 megawatts (MW) 10 years ago this summer. At the time, rising demand and plans to retire its coal-fired power plants dominated provincial energy policy. What followed was optimism for a new energy policy, focused on the ambitious procurement of large wind and solar installations. I felt great pride in helping to lead an industry that would make Ontario’s power system clean, responsive and cutting edge.
What a difference a decade makes. Intrusive policy and poor implementation are largely responsible for the energy market debacle Ontarians face today. But there is no excuse now for buying more mega-projects when our power supply is saturated and hydro bills are skyrocketing.
Coal-fired power generation effectively disappeared after 2010, by which time Ontario’s electricity demand had already started to plummet. Demand has fallen 13 per cent in the past 10 years, including consecutive reductions in each of the past five years. In 2016, Ontario will consume less electricity than in 1997.
Peak demand exceeded 23,000 MW only one day this summer, despite parts of the province seeing 35 days with temperatures above 30 C. Yet our installed capacity approaches 40,000 MW. The system will have reserves above extreme summer peaks well into the 2020s. The Independent Electricity System Operator (IESO) reinforced this point recently when it confirmed “Ontario will have sufficient supply for the next several years.”
Against this troubling background, the Ontario government is procuring an additional 1,300 MW of large wind and solar generation under the Large Renewable Procurement (LRP) program. This decision is indefensible. It makes the frequency of negative pricing (paying our U.S. neighbours to take Ontario energy during periods of low demand) and curtailment (paying wind developers for energy production even when the grid can’t use the power) even worse. These problems have become billion-dollar burdens for Ontario electricity customers.
Sweet contracts, painful electricity bills
Offering sweet contracts to large renewable energy developers while demand stagnates has helped push hydro bills higher. Electricity prices have increased by seven per cent a year since 2009. Costs have risen faster than Ontario’s inflation rate in each of the past several years. The province’s electricity rates are increasing faster than any other jurisdiction in North America.
It’s clear that change must begin with the renewable industry, since our industry alone benefits from the continued overprocurement of electricity. The fact is large wind and solar developers have been pampered by Queen’s Park for far too long. Although solar installation costs dropped 70 per cent in the past decade, the government froze prices for years at a time. When permitting delays enabled projects to be built as much as five years after contracts were awarded, multi-millionaires were created overnight.
Today, with no logical reason to build more wind and solar mega-projects in Ontario, renewable developers must confront the economic damage they are doing to their families, friends and neighbours, and to the next generation of citizens who will bear the brunt of this green corporate welfare.
Renewable energy companies must confront the economic damage they are doing.
We need to make four changes. First, Ontarians must demand a return to basic electricity policy principles: safety, reliability and cost effectiveness. Second, the government should revisit the IESO’s legal obligations associated with the current LRP process and exit this procurement process without paying the ransoms that characterized Ontario’s gas plant debacles. Third, the IESO should restrict renewable procurement to the smaller rooftop and distributed energy projects that actually benefit customers. Fourth, Ontario renewable energy firms must learn to export their pioneering expertise and target new domestic and international markets.
The global renewable energy revolution has just started. Solar energy is increasingly the cleanest, cheapest and most environmentally sustainable option. The advent of battery storage, smart grids and the Internet of Things will catalyze innovative economies that embrace change. Renewables have a bright future in this world, but we need to regain control of Ontario’s failing electricity policies — and do it soon — to ensure we seize the energy opportunities of the 21st century.
National Post
Jon Kieran is a Toronto-based renewable energy consultant. He is a member of the Canadian Solar Industries Association’s board of directors. He declines LRP work from clients.
The Windlectric wind power project on tiny Amherst Island has no hope of meeting its “drop-dead” Commercial Operation date, so Ontario’s Independent Electricity System Operator (IESO) can cancel the Feed In Tariff (FIT) contract right now, with no penalty, says the Association to Protect Amherst Island.
See the letter to IESO Chair Tim O’Neill here and below.
Dear Dr. O’Neill,
In August 2015 The Association to Protect Amherst Island requested that the IESO exercise its ability to cancel the Fit Contract dated February 25, 2011 with Windlectric Inc. (Algonquin Power) without penalty because of the inability of the company to achieve its commercial operation date.
In its 2016 Q2 Quarterly Report, extract attached, Algonquin now advises that construction is expected to take 12 to 18 months and that the Commercial Operation Date will be in 2018. This timeline is contrary to what was submitted to the Environmental Review Tribunal and to the Ontario Energy Board. A COD of 2018 is seven years from the date of award of the contract.
Cancellation of the contract at this time would enable the IESO to achieve cost avoidance exceeding $500 million over the next 20 years based on the high cost of power generation at 13.5 cents per kilowatt-hour set out in the contract with Windlectric and based on the IESO’s commitment to pay Windlectric to not produce power when capacity exceeds demand. Cancellation of the Windlectric contract could be achieved without penalty due to noncompliance and would address in part the IESO’s budget challenges and energy poverty in Ontario.
Accordingly, the Association reiterates its request that IESO cancel the FIT Contract with Windlectric Inc.
Rick Conroy, in the attached article from the Wellington Times, explains the Kafkaesque and cruel nature of allowing the Amherst island project to continue especially in light of the unused power capacity of the nearby Lennox Generating Station and the Napanee Gas Plant under construction.
In summary:
• Windlectric cannot comply with the Commercial Operation Date in its FIT Contract.
• At a time of skyrocketing hydro rates and financial challenges the IESO could save $500 million over the next 20 years by cancelling the Windlectric Contract without penalty.
• Existing nearby generating capacity is almost never used and will increase when the Napanee Gas Plant comes online. Intermittent and expensive power from wind turbines on Amherst Island is not necessary
Finally, please provide the IESO’s understanding of the Commercial Operation Date for Windlectric, any extensions awarded by the IESO, and the number of days granted due to Force Majeure and judicial matters.
A citizens’ group concerned about the effect of wind turbine construction and the vibration coming from operating turbines is calling for the resignation of the Ontario Minister of the Environment.The government’s response to the problem of damaged wells? Bottled water. Not so great for dairy herds…
A citizens’ group worried about the potential impact on groundwater from wind turbine vibrations is calling for the provincial minister’s resignation.
Water Wells First placed protest signs on Monday at the Windsor, Sarnia and London offices of the Ministry of the Environment and Climate Change, said group spokesman Kevin Jakubec in a media release..
“Water Wells First no longer sees the MOECC as credible stewards of the environment.
We are asking for the immediate resignation of Ontario’s Minister of the Environment and Climate Change Glen Murray,” he said.
Last week, Water Wells First held a demonstration at a Chatham Township farm to show how difficult it would be logistically for farmers and their livestock to use bottled water, if it was required.
Jakubec said the management of the Renewable Energy Program could jeopardize the health and safety of Ontario’s livestock when “the MOECC put forward the impractical use of using bottled water to resupply livestock farms” that have lost their water wells due to wind farm construction and operation.
The proposed North Kent 1 Wind Project, which calls for 40 to 50 wind turbines to be constructed in the area, had some residents worried that the vibrations could result in dirty water.
“Water Wells First will protest the actions of the MOECC until the MOECC recognizes that groundwater must be protected as the first line of defense against climate change,” Jakubec said.
Last month, the group held an initial media conference to help raise awareness about the issue.
In an e-mail on Monday, the ministry stated that it was taking the necessary precautions.
“The MOECC takes all public concerns very seriously. That is why MOECC included an extremely stringent series of conditions on the proponent for the North Kent Renewable Energy Approval,” it stated. …
See also a London Free Press editorial on this today, here.
Editor’s note: looking ahead, we would think this might be a concern for liability on the part of both the landowner leasing land for turbines and the wind power developer. Another reason to carefully examine the pro’s and cons of signing a lease agreement.
“Overwhelmingly fraudulent”; “we were ready with a team of lawyers”; “property values are decreased because of forced wind turbine projects” … and more.
Ontario community groups, municipal representatives and individual citizens responded to the Independent Electricity System Operator (IESO) request for feedback on its renewable power bid process.
The IESO published a summary of comments received in its online survey, yesterday.
Ottawa Wind Concerns was among the community groups responding to this survey.
Key issues were the fact that the process was difficult to understand, unfair to individuals and communities, and that so-called “community engagement” was a false promise, given that community support (or lack of it) was just one of the rated criteria in the bid process, not a mandatory requirement.
Municipal governments are forced to determine whether they support a power project with very little information, representatives said. The rated criteria activities to indicate community support were ineffective, said most of the municipal government representative responding: 70 percent said the activities prescribed were “somewhat” or “very” ineffective.
The mandatory meeting was set up in a format that was to leave everyone with the least amount of say as possible. There were large displays set up showing the project. There was no intention for any real interaction with the participants. We had to basically demand a question and answer period. Questions and answers in a public format is the way these mandatory meetings should be set up to ensure that the correct info is actually being presented.
The mandatory community engagement requirements and optional rated criteria community support activities were neither clear nor successful in raising awareness within the Project Community. How can a requirement to consult members of a community (and having owners sign a support form) on an existing line that had already been fully and duly permitted and that represents no new or additional impact for them be considered mandatory and successful in raising awareness or support for the project? The Rated Criteria points associated with obtaining a support resolution from the municipal council gives too much negotiation leverage to the Municipalities. Rated Criteria points should also be allocated following a prorated basis instead of a all or nothing basis, especially the ones associated with abutting landowners support.
Some respondents questioned the municipal support process, saying that councils ignored community wishes and/or had pecuniary interests in the proposed power projects.
I was part of the General Public who attended meetings and proposal meetings. Our elected officials were not responsive to the general public opinion which was 80% plus against the proposal so we had to fight our representatives. The process was very poor and at least 1 of our political persons refused to withdraw from voting and would directly benefit from the projects if approved. I felt like I lived in a 3rd world country.
Other respondents decried the loss of good Ontario farmland for power projects, and the social impact on communities when some landowners took out leases or accepted payments for support of abutting power projects.
Another concern was the communities and neighbours to power projects had no idea the bid was coming until it was put together.
Very simple. Let communities decide whether they want these projects or not. Let neighbors know from the very outset that their communities are being considered. Holding a propaganda session once the project is ready to be submitted is not community involvement.
As the Ontario government prepares to open a second, more ambitious round of bidding on large-scale renewable energy projects across the province, some Ottawa city councillors want more local control over where wind farms go.
“There’s no way for a municipality to express concerns about location, or if and when these projects would happen in our municipalities,” said Scott Moffatt, who represents the rural ward of Rideau-Goulbourn.
In March Ontario’s Independent Electricity System Operator awarded contracts to 16 renewable energy projects, three quarters of which had support from the local municipality, the government said at the time.
Five of the contracts were awarded to wind projects, including the 100-megawatt Nation Rise Wind Farm in North Stormont Township, a municipality which had previously declared itself an “unwilling host” to wind farms.
A motion approved Thursday by councillors on Ottawa’s agriculture and rural affairs committee urges the province to strengthen legislation to require municipal buy-in before contracts are awarded.
Communities want a voice, councillor says
Moffatt said communities want a voice in the planning process.
“This isn’t just for Ottawa. We’ve had this issue in the past in Ottawa, specifically in North Gower, but you look at Nation, you look at South Dundas and Brinston,” said Moffatt, describing proposed wind farm locations.
“Are those municipalities able to respond adequately or is the IESO just going to run roughshod over them? That’s the concern.”
In an email, a spokesperson for Ontario’s Energy Ministry said the government is proud of the 75 per cent support rate from municipalities for its first round of contract offers, and noted 60 per cent of neighbouring landowners also supported them.
“By putting emphasis on price and community support, we believe the right balance has been struck in early community engagement and reduced prices for consumers through the procurement process for renewable energy projects,” wrote the spokesperson.
930 megawatts sought in 2nd round
The IESO is gathering feedback on its first competition, and could use that information to fine-tune the process the second time around.
The Ontario government intends to issue a request for qualifications by August for projects that can generate a total of 930 megawatts of renewable energy, two thirds of which will go to wind farms.
That’s more than twice the size of the initial contract offer.
The ministry’s ultimate goal is to have 10,700 megawatts of wind-, solar-, and bioenergy-powered projects feeding the grid by 2021.