Public meeting in Finch on Wednesday

03 Sunday May 2015

Posted by ottawawindconcerns in Ottawa, Renewable energy, Wind power

≈ 2 Comments

Tags

Brinston, EDP Renewables, Finch Twp, Prowind, South Branch, South Dundas, Stormont Dundas and Glengarry, wind farm

The power developer who bought the 30-MW South Branch project in South Dundas from German developer Prowind, EDP Renewables, is now proposing to expand into Stormont, Dundas and Glengarry, and apply for a Feed In Tariff contract. Spokesman Ken Little told South Dundas council the company was planning 30-50 turbines.

Ontario is currently offering contracts for 300 MW of new wind power in 2015, despite a situation of surplus power in Ontario, and the fact that Ontario lost more than $425 million in the first quarter of 2015, exporting surplus power cheap.

A public meeting will be held in Finch this coming Wednesday at the community centre/arena at 7 PM. The goal is to have a panel present various viewpoints on wind power.

Guest speakers will be Tom Levy of CanWEA, Jane Wilson of Ottawa Wind Concerns /Wind Concerns Ontario, and Don McCabe of the Ontario Federation of Agriculture.

EDP’s Brinston project is about 40 minutes south of Ottawa.

ottawawindconcerns@gmail.com

$70-million charge on Brinston farm titles for wind farm

28 Tuesday Apr 2015

Posted by ottawawindconcerns in Ottawa, Renewable energy, Wind power

≈ 10 Comments

Tags

Brinston, Charge of Lease, demand debenture, leasing land for wind turbines, Prowind, South Dundas, Stormont Dundas and Glengarry, wind farm, wind farm financing, wind farm leaseholders, wind farm leases, wind power, wind turbines

 

Construction of one of the 3-MW turbines at Brinston--30-50 more proposed by EDP Renewables

Construction of one of the 3-MW turbines at Brinston, now operating–30-50 more proposed by EDP Renewables

Ottawa Wind Concerns has learned that a “Charge of Lease” has been placed on the South Branch wind “farm” in the amount of $70 million. The charge is on the leasehold interest in five properties, where property owners have leased land for wind turbines, access roads, substations, and other parts of the wind power generation project.

Earlier this month, details came to light on the 140-turbine K-2 project near Goderich, Ontario, where a charge of lease has been filed on the title for 100 farm properties, in the amount of $1 billion.

The Charge of Lease is basically a financing agreement between a lender (who may represent investors in the wind power project) and the wind power developer, that can function as a line of credit. The basis for the Charge, as we understand it, is that the present value of the contract for the turbines, i.e., the Feed In Tariff contract for power with the Province of Ontario is greater than the present value of the lease agreements with the landowners; the difference between those two values is the security for the loan.

The South Branch contract with the Ontario government runs for 20 years and is worth millions to the developer, who bought the project from Germany-based Prowind.

The importance of the existence of these agreements is the effect they have for the landowner leasing land for the wind turbines. In the opinion of a lawyer advising us (who prefers the term “Demand Debenture” for this arrangement:

It’s not so much that the farmer lessors might on default lose their land (the land itself is not mortgaged, just the turbine contract on that land) but the damage it does to that farmer if he/she wants to sell or to renew an existing mortgage, or place a new one or in any way borrow money for which the lender would want security on his/her land.

Assume a binding Agreement of Purchase and Sale. The lawyer for the purchaser does a title search and discovers the Demand Debenture. The lawyer would immediately tell his/her client that the client is entitled to get out of the deal unless the registration of the Demand Debenture is removed from title, and would also insist to the farmer’s lawyer that this be done otherwise the deal cannot close. A purchaser is not expected to assume any risk of this nature nor to be in the position of “buying a law suit”.

in the case of renewing an existing mortgage or placing a new one, the lawyer for the Bank or other lending institution would take the same position – no renewal or new mortgage unless the customer sees to it that the Demand Debenture disappears from title. Period. End of story.

This is another example of the very serious questions that need to be asked by anyone considering leasing their land for a wind power generation project. There are many serious and long-lasting effects to signing these agreements that need to be properly understood.

In 2013, the Not A Willing Host group of municipalities met in Ottawa at the Association of Municipalities of Ontario convention. At that meeting, one Ontario mayor said, What people need to understand is that basically, they sold their property for the amount of the lease agreement.

** Please see also, the article from the May 5th edition of Ontario Farmer on the charge of lease issue, here.

Massive wind farm proposed south of Ottawa

24 Friday Apr 2015

Posted by ottawawindconcerns in Ottawa, Renewable energy, Wind power

≈ 2 Comments

Tags

Brinston, Eastern Ontario wind farm, EDP Renewables, Not a Willing host, Otatwa, South Dundas, surplus power Ontario, wind farm

 

 

Cornwall NewsWatch, April 21, 2015

Next South Dundas wind farm could be four-fold of South Branch: EDP

Posted on April 23, 2015 by Editor in News, South Dundas // 0 Comments

EDP Renewables Project Manager Ken Little, left, and Deputy Project Director Thomas LoTurco make a presentation to South Dundas council April 21, 2015. The company responsible for the South Branch Wind Farm is planning on building another farm east and north of Brinston, Ont. (Cornwall Newswatch/Bill Kingston)

MORRISBURG – The next wind farm in South Dundas could be up to four times the size of the South Branch Wind Farm, township officials heard Tuesday night.

EDP Renewables made a presentation to council to update the municipality on its next steps to build another wind farm in the county and ask for its support for the project through a “community support resolution.”

While no decisions were made Tuesday night, it’s unlikely that South Dundas will put pen to paper to back the wind farm as it signed a resolution in the fall of 2013 to tell the Ontario government is was a non-willing participant in wind energy.

EDP already has a 10 turbine, 30 megawatt operation – the South Branch Wind Farm – near Brinston.

Spokesman Ken Little says they will have a better idea how big the project will be when the Independent Electricity System Operator (IESO) publishes the grid connection availability, expected on May 22, 2015.

But, based on EDP calculations, they are assuming the capacity will be 50-100 megawatts, which could be serviced by 40 windmills.

Unlike the South Branch Wind Farm, this next farm is part of a competitive bid process and not under the Ontario government’s feed-in-tariff (FIT) program.

It would be east of the South Branch Wind Farm and would stretch in a northeasterly direction toward Winchester Springs.

Little says it’s likely the area would also be eligible for a community investment fund, similar to the one in Brinston, of $1,000 per megawatt per year for 20 years.

He also alluded to jobs, saying the operations are supported right now out of their New York office. “If we were to have another project in the area we would be talking about our own fully-dedicated operational staff full-time for those projects as well.”

“We’re going to start our public open houses in late May,” Little told council Tuesday night. “These will be general in format just to discuss the project and folks to ask questions.” Dates haven’t been set but they will mostly like be held at Matilda Hall or the Dixons Corners Municipal Center.

Little says there’s going to be a bigger demand for wind power in the years ahead. “With the Ontario energy surplus, it’s always a hot topic for discussion, it’s something where were closely getting to a window where that surplus will no longer be a surplus,” he said. The Pickering nuclear plant will be shut down in 2020 and 10 Bruce and Darlington nuclear plants, will be cycled off for rebuilds between 2017-2028, he explained.

For the green energy skeptics and the curious, EDP officials say the existing operation in Brinston is open for tours from the public at any time.

EDITOR’S NOTE: EDP is referring to the issue of surplus power in Ontario because that is the fact that the South Dundas unwilling host motion hinges on. The truth is, wind power–produced out-of-phase with demand, intermittent and unreliable–cannot replace the nuclear plants during their period of refurbishment. That would more likely be achieved by the natural gas plant at Lennox, and hydro.

An information evening will be held May 6th in Finch at the Lions Arena, at 7 PM.

Developer says more wind turbines coming to North Stormont, South Dundas

10 Tuesday Mar 2015

Posted by ottawawindconcerns in Renewable energy, Wind power

≈ 1 Comment

Tags

EDP Renewables, IESO, Ken Little, North Stormont, South Dundas, South Dundas wind farm, wind farm Eastern Ontario

Cornwall News Watch, March 9, 2015

More wind farm plans for S. Dundas, N. Stormont

Posted on March 9, 2015 by Editor in News, North Dundas, North Glengarry, North Stormont, South Dundas, South Glengarry, South Stormont // 1 Comment

South Dundas Mayor Evonne Delegarde, left, shakes the hand of EDP Renewables Project Manager Ken Little. The company announced $2.7 million in compensation to Dundas and SD&G for road damage during the construction of the South Branch Wind Farm. (Cornwall Newswatch/Bill Kingston)

MORRISBURG – While announcing a settlement for road damage in Dundas county, the company behind a 10 turbine, 30 megawatt wind farm in Brinston is looking to expand.

During a ceremony at the South Dundas Municipal Center Monday afternoon, EDP Renewables paid Dundas and the United Counties of SD&G nearly $2.7 million for road wear when they put up the South Branch Wind Farm near Brinston.

The process started in June 2013 when North Dundas, South Dundas and the United Counties signed road use agreements with EDP.

Following an engineer’s evaluation, EDP agreed to pay South Dundas $868,500, North Dundas $118,590 and the United Counties $1,697,386.

Compensation a ‘drop in the bucket’

While the Municipality of South Dundas appreciates the money, Public Works Manager Chris Bazinet says the compensation is “just a drop in the bucket” given the cost of the roads and maintaining infrastructure.

While the money can be used at the municipal governments’ discretion, South Dundas Deputy Mayor Jim Locke says the county money is earmarked for South Dundas county roads.

With the damage compensation out of the way, EDP Renewables Project Manager Ken Little says they are looking at options in South Dundas and North Stormont.

Little says the next rollout of wind farms will be a competitive bid process run by the province but it will not fall under the Ontario feed-in-tariff (FIT) model.

He says they have already approached some farms about optioning land, primarily in the area east of South Branch Road in South Dundas.

“(It’s) still an early stage project. But we’re working with the IESO (Independent Electricity System Operator) to understand what the capacity, availability is in all of Eastern Ontario. So, it’s at a stage where no proponents necessarily know the amount of capacity available for a project to connect to the circuit,” Little said.

He believes a screening process will be completed in May, which will give the public a better idea of the size of project.

Roughly 30-50 wind turbines had been planned for North Stormont but Little suspects the development with South Dundas would be smaller than that.

Bids on the project would be due in September and proposed wind farms would go online in 2018-2019.

………………………………………..

Editor’s note #1: WHY does the wind power developer’s payment of funds owing due to road damage rate a “ceremony”?

Editor’s note #2: The South Branch Wind Opposition Group in South Dundas has disbanded; for more information or assistance, please contact Ottawa Wind Concerns at ottawawindconcerns@gmail.com or Wind Concerns Ontario at windconcerns@gmail.com

How much does it cost to demolish a wind turbine?

14 Tuesday Oct 2014

Posted by ottawawindconcerns in Ottawa, Renewable energy, Wind power

≈ 1 Comment

Tags

Brinston, Canadian Hydro Developers, decommissioning, decommissioning costs turbines, EDP Renewables, Farmers Forum, Prowind, recycle turbine parts, South Dundas, Tom Collins Farmers Forum, Trans Alta, wind farm leases, wind turbine, wind turbines, Windlectric, Wolfe Island wind farm

Re-posted from Wind Concerns Ontario; note the information on the Brinston wind power project.

How much to take down a wind turbine?

Bonanza in scrap, or millions to demolish?
Bonanza in scrap, or millions to demolish?

Tom Collins, Farmers Forum, October 2014

Scaremongers say it will cost millions

Brinston–While some critics of wind turbines howl that the cost of the eventual teardown of a turbine is astronomical, the actual cost today would be $30,000 to $100,000, per turbine.

The bigger issue is, who is going to pay for it.

Municipalities are on the hook to ensure companies tear down or, in industry jargon, decommission a turbine, unless they’ve got a binding agreement with the wind power company. Some municipalities demand from wind turbine companies ongoing payments into protected (or escrow) accounts or bonds to set money aside annually to pay for decommissioning.

Some municipalities require a letter of intent from wind turbine companies to ensure they will be responsible for decommissioning. Some municipalities have no agreement at all, including Wolfe Island, said its mayor, Denis Doyle. TransAlta communications manager Stacey Hatcher said the decommissioning plans are between the company and the landowner and because of that, the info is confidential. [See editor’s note #1]

The 86 turbines on Wolfe Island, on the St. Lawrence River at Kingston, were built by Canadian Hydro Developers, later purchased by Trans Alta and there is no bond or escrow account in place. The company does, however, reimburse the island about $100,000 per year for hosting the project. Based on current decommissioning projects around the world, it can cost $30,000 to $10,000 [sic] to dispose of a turbine. If it were to cost $50,000 to remove each turbine on Wolfe Island, it would cost $4.3 million to remove them all. Of course, that price goes up over time. [See Editor’s note #2] Hatcher said the company plans to repower or recontract when they [sic] current contracts are up.

There are 10 three-megawatt wind turbines at Brinston, between Kemptville and Winchester, and the power company ProWind [see Editor’s note #3] pays $1,000 per megawatt per year over the next 20 years into an escrow account that will rack up $600,000 to pay for decommissioning. [Editor’s note #4]

Windlectric Inc. wants to build 36 turbines on Amherst Island where Statec Consulting said that decommissioning costs are up to Windlectric. Typically, decommissioning will not remove all of the concrete base, but that’s only the first few feet of concrete that went into the ground. [We’re done adding editor’s notes at this point.]

One of the most infamous decomissionings involved 37 decrepit turbines in Hawaii that stood unused for six years before they were taken down in 2012. Tawhiri Power estimated that the take-down cost $30,000 per turbine. [OK, one more; see Editor’s note #5]

The seven-turbine community-owned Black Oak Wind Farm in New York State will start construction in late 2014. The decommissioning plan would currently cost about $55,883 per turbine, although the project expects to generate at least $50,000 per turbine by selling it as scrap metal. The municipality agreement means the power company must pay $140,000 per turbine in escrow but also means the payment can be reviewed and changed if decommissioning estimates change.….

WCO Editor’s notes:

1. Many landowners were told that it was to their benefit to decommission the turbines themselves as there is so much scrap value in the turbines; this is untrue due to the quality of metal being used, and also the other costs of decommissioning such as crane rental, and disposal of the toxic components.

2. So, that would be the millions then…

3. ProWind, properly “Prowind,” does not own the Brinston project, and hasn’t for several years. It is now owned by EDP Renewables.

4. In the original negotiations with Prowind, the developer wanted the landowners and the municipality to be responsible for decommissioning costs. It was the local community group that brought these costs to the attention of the municipality, and played a significant role in the agreement now in place.

5. US dollars? Canadian dollars? Also, the size of the turbines and the machinery involved is a factor. The turbines erected in Hawaii over a decade again, and the turbines at Wolfe Island are now miniscule compared with the 500-foot-plus, 3 -MW behemoths being built and proposed.

Write to Farmers Forum at editor@farmersforum.com

Brinston wind farm noise prompts MoE investigation

11 Monday Aug 2014

Posted by ottawawindconcerns in Renewable energy, Wind power

≈ 1 Comment

Tags

Brinston wind farm, EDP, EDP Renewables, infrasound, Leslie Disheau, Ontario Ministry of the Environment, sleep disturbance, South Branch wind farm, South Dundas, wind energy, wind farm, wind farm noise, wind power, wind turbines

Turbine neighbour prompts noise probe by ministry

By Nelson Zandbergen – AgriNews Staff Writer, August, 2014

Ontarios Ministry of Environment and Climate Change installed the basketball-sized microphone atop a temporary 30-foot listening post in her backyard, along with a smaller meteorological tower.BRINSTON Leslie Disheau has her ear to the ground in South Dundas, and for 10 days last month, a very powerful ear trained on the sky around her Brinston home as well.

The ministrys move was prompted by Disheau and partner Glen Baldwins complaints about nighttime noise emanating from two industrial wind turbines on either side of their place, one to their immediate northwest, the other to the southeast. Comprising part of the 10-turbine South Branch project that went into serviceearlier this year, both of the nearest units are less than one kilometre away from the home the couple shares with their two teenaged children.

But Disheau, candidate for deputy mayor in the municipal election and a fierce critic of the turbine industry, feared that developer EDP Renewables was intentionally slowing the two windmills to quiet them down while the ministry data-collection and audio-recording effort was underway with her participation.

The Houston-based firm almost immediately learned about the microphone on the day of the install, she said with some frustration.

Located just down the road from the projects main depot, it wasnt more than three hours after the arrival of two ministry trucks in her driveway that EDP called the same ministry to question the presence of those vehicles, according to Disheau.

She says the audio technician putting up the equipment learned of EDPs inquiry while talking to his office bycell phone, then told her about it.

Wind developer has not filed a compliance report yet

Disheau expressed unhappiness that a mandatory post-construction noise report had yet to be publicly filed by the company itself, after putting the project into service in March.

In the meantime, over a 10-day period in July, the ministry captured its own sound data with Disheaus help. During those times she considered the turbines to be noisiest, she pressed a button inside her home, triggering the recording process via the outdoor microphone, which was tethered to audio equipment in a locked box.

Comparing the sound to that of a rumbling plane or jet, she got up at night when she couldnt sleep to push the audio recording button located at the end of a long cord connected to the stuff outside. She also kept an accompanying log as part of the initiative.

The noise is most acute, she said, when the direction of the wind causes the blades to swivel toward her home in perpendicular fashion.

Effect of multiple turbines not considered by government

She scoffed at regulations that mandate 500-meter setbacks to neighbouring homes, pointing out the rule doesnt take into account the cumulative, “overlapping” impact of multiple turbines that surround. Nor does the regulation change with the actual size of a turbine, she adds, asserting that, at 3-megawatts apiece, “these are the largest turbines in Ontario.”

Ultimately, the ministry will use the data collected by Disheau to create a report, which could potentially form the basis of ministry orders against the two offending turbines. “To shut them down at night so that people can sleep,” she said with a hopeful tone, though she also acknowledged the ministry may not issue orders. And even if it does, she expects the developer to appeal and appeal.

Disheau also said there are measures that municipal governments can undertake to curtail the noise, including a nuisance noise bylaw of 32 decibels, which recently survived a court challenge in another Ontario municipality. She espouses such a policy in South Dundas and will push for it at the council table if elected.

Read the full story here.

Email us at ottawawindconcerns@gmail.com

Brinston wind farm noise complaints lead to monitoring

28 Monday Jul 2014

Posted by ottawawindconcerns in Health, Ottawa, Renewable energy, Wind power

≈ 1 Comment

Tags

Brinston, EDP Renewables, infrasound, MOE, MoE Spills Line, Ontario Ministry of the Environment, Ottawa area wind farm, South Branch wind farm, South Dundas, wind farm, wind farm noise, wind power, wind turbines

And this is a SMALL one...

And this is a SMALL one…

The South Branch wind “farm” has been operating since mid-March, but it didn’t take long for the first noise complaints to be registered. This wind power generation facility is the first of the 3-megawatt machines to operate in Ontario; many more, mostly in southwestern Ontario, are to follow. The increased capacity is a concern to people who have done research on wind turbines, as they are more likely to produce infrasound or sound pressure, which disturbs some people.

Noise complaints lead to monitoring

by Sandy Casselman
Press staff

BRINSTON – It has been more than six months since the blades of the South Branch Wind Farm turbines began to spin, leaving more than one nearby resident with some sleepless nights.

“I call when it gets to the point I can’t tolerate it anymore and I go to the basement [to sleep],” Brinston resident Leslie Disheau, former president of the South Branch Wind Opposition Group, said. “It is an issue and I’m not the only person in town with the issue.”

Disheau, who is running for the Municipality of South Dundas’ deputy-mayor seat in this fall’s municipal election, has been staying close to home since the Ministry of the Environment (MOE) installed noise-monitoring equipment at her Brinston Road property last week.

“MOE contacted me and asked if they could put this noise monitoring equipment up,” Disheau said.

The two pieces of equipment measure wind speed and direction, barometric pressure, rainfall, and more, she said.

She has submitted three separate noise complaints so far. Every complaint must be filed with EDP Renewables’ project leader Ken Little and local MOE representative Terry Forrester to be officially registered.

During EDP’s first open community liaison meeting in March, a Brinston man spoke out about his own sleep disturbances, suggesting the turbines be shut off for a period during the early hours of the morning, beginning around midnight. At that time, Little confirmed that there had been one official complaint already registered. He also said an acoustic audit had been ordered, which he expected to get underway within two months of the meeting.

“EDP has not released their post-construction noise audit report,” Disheau said during an interview with the Winchester Press Fri., July 18.

In conversation with one of the MOE officials who installed the equipment, Disheau said she learned that the provincial authority also had not seen a report from EDP.

“They can take a long as they want,” she said, crediting the Green Energy Act with the responsibility for not specifying a deadline. “There is a 40-decibel limit [on the noise the turbines can make], and we have no idea if they’re in the threshold or not.”

To describe what the sound is like, she used Highway 401 versus airplane noise as an example, pointing out that the highway noise is more of a hum, and when she lived near it, the sounds did not bother her at all.
However, the turbines produce something more in line with the “drone of an airplane that goes into your head,” she said. “It’s a deeper tone, and that’s where you get the disturbance of sleep.”

Explaining the noise and its effects on her is not easy, she said, but it is similar to the sensation people get in their chest when listening to bass guitar.

Disheau said she explained her experiences to MOE’s acoustical engineer, adding that the sensations are at their worst when the blade tips of the turbine across the road (south of Brinston) and the one to the north behind her home (west of Brinston) are facing one another.

“The acoustical engineer said ‘yes, that it all makes sense,’ ” Disheau added. “This is not normal. You should not be in sleep disturbance in your own house.”

Meanwhile, Disheau is the only one in her home experiencing the effects of the rotating blades, as her husband, who shares the second storey bedroom on the home’s vinyl-sided addition, is tone deaf, and her children sleep on the first floor of the brick-sided main house.

The noise-monitoring equipment is controlled by a switch, which has been placed inside Disheau’s home. When she notices the noise, she flips the switch and the machinery calculates and documents the findings.

“Once everything is taken down, the ministry guy goes through [the recordings] and writes his report,” she said, which will list the decibel readings for various weather conditions (wind speed and direction).

When asked what she hopes to accomplish through this procedure, Disheau said the findings could require that EDP shut down operations during specific times of the day or during specific wind conditions should they prove the decibel levels exceed the regulated amount.

Read the full story here.

People with complaints about excessive noise from the turbines at Brinston must call both the developer, EDP Renewables (1-877-910-3377 ext 3) AND the Ministry of the Environment (1-800-860-2760). 

 

CanWEA execs venture down to Brinston wind ‘farm’

17 Thursday Jul 2014

Posted by ottawawindconcerns in Health, Ottawa, Renewable energy, Wind power

≈ 1 Comment

Tags

Brinston, Canadian Wind Energy Association, CanWEA, Eastern Ontario, EDP Renewables, law suits wind farms, legal action wind farms, property value, Prowind, sleep disturbance, South Branch, South Branch Kid Wind Day, South Dundas, wind farm, wind farm noise, wind power, wind turbines

 

 

Not from around here: just visiting for the brainwashing

The executives at the wind power developers’ lobby group, the Canadian Wind Energy Association, took a trip down the road from their offices on Carling Avenue in Ottawa to see the wind power project in Brinston, just south and east of Ottawa.

Here’s a report on the visit:

CanWEA Staff Tours South Branch Wind Farm

On June 25, several EDPR employees led a tour of the South Branch wind farm for staff members of the Canadian Wind Energy Association (CanWEA) , including CanWEA’s president, Robert Hornung, who had this to say about the visit: The siting characteristics of South Branch and how well the wind farm blends with the natural landscape are truly impressive, said Mr. Hornung. We were equally impressed by the care and attention that EDPR has taken in building a high level of enduring community acceptance. 
The tour of the wind farm, located near Brinston, Ontario, included stops in the O&M building as well as the inside of the base of a tower and the substation building. After an informative tour, CanWEA expressed interest in working with EDPR to improve its information packages for farmers.  Several CanWEA representatives also said they planned to stop by the upcoming South Branch Kid Wind Day, which will be held on Thursday, July 24, and attended by 150 kids.

The claim that EDP has “enduring community acceptance” would be laughable, were it not for the truth about this community: once the wind project was publicly announced by the original developer, Germany-based Prowind, the community became divided between the few farm owners leasing their land for turbines, and others in the community who had no choice but to watch this happen to them. A community group was organized and held several information meetings…but of course, with the Green Energy Act, there are no solutions through elected representatives. South Dundas Council voted on a resolution to say there would be no support for further wind power development as Ontario doesn’t need any more power generation.

The so-called South Branch Kid Wind Day is NOT for local families (hard for them to miss the huge, 3-megawatt turbines) but it will be for kids being bused in from elsewhere. The community has not even been informed of this PR event.

Of greater concern, though, is the news that an “information package” is being developed for farmers: this is being worked on because Eastern Ontario has a green light from the province for wind power development…it is rumoured that 5,000 more acres in North Dundas have been optioned for future wind power development.

Our question: will EDP and CanWEA provide full disclosure on noise, health problems, sleep disturbance, property value loss, and the potential for lawsuits from neighbouring landowners?

Email us at ottawawindconcerns@gmail.com

 

South Branch wind project footprint visible

16 Wednesday Oct 2013

Posted by ottawawindconcerns in Renewable energy, Wind power

≈ 1 Comment

Tags

AgriNews, Brinston, cost-benefit renewable power, environmental damage wind power, Green Energy Act, land used for turbines, Not a Willing host, Ontario Municipal Act, payment for non-production wind power, South Branch wind project, South Dundas, Steve Byvelds

From the October edition of The AgriNews, an update on the South branch wind power project. You recall that Prowind, the same developer as for the Marlborough project in North Gower, began this project by leasing land from local farm owners, and then sold it to Portuguese energy giant EDP. Construction is ongoing now.

Here is an excerpt of the story by Lois Ann Baker.

BRINSTON–Now that the wet weather is out of the way, construction on the South Branch Wind Farm* is well underway. The sites of the 10 turbines that will be scattered throughout the Brinston area have been excavated and access roads have been created to allow the many trucks and equipment to access the sites.

Within the next week or two the foundations for the turbines will be poured, paving the way for installation of the turbines.

The main site located on Brinston Road just south of the hamlet, will also be home to the substation that will be used to maintain the turbines. A building consisting of meeting rooms and storage space will also be located on that site.

Project manager Ken Little said … the turbines [will] be installed in November and they should be producing power for Hydro One by the new year.

The controversial wind farm has sparked interest among the locals, said Little and EDP Renewables has tried to keep up “fairly regular communication” with both supporters of the project and those that oppose the turbines.

Ralph Butler of Williamsburg expressed his concerns over the wind farm by saying that the area of farm land being wasted is unbelievable.

BrinstonAerialSB“I think it’s the biggest waste of money since the gas plant,” said Butler. “I’ve been complaining about this ever since it started.”

Butler added that with new regulations brought in by the Ontario government stopping the turbines from producing power when there is an abundance of power on the grid, it’s possible these turbines will never turn a blade to produce power. He also added that the municipal government should have done something to stop the project.

[EDP’s] Little didn’t seem overly concerned with the regulations saying that…they will be compensated. “If we are asked to shut them down, after a certain amount of time we will be paid,” said Little.

In light of these new regulations, South Dundas council passed a resolution at the first regular council meeting held after the groundbreaking of the turbine sites to not support any future proposals until the supply and demand for electricity demonstrates a need. Council had previously turned down a resolution by Councillor Evonne Delagarde requesting that the municipality become known as “Not a Willing Host” to industrial wind turbines.

At the same council meeting, council felt the need to defend themselves when long-time Brinston resident Robbie Giles gave a presentation on how he felt council had no been open and acted in the best interests of residents of South Dundas, with regards to the South Branch project. Giles claimed too many informal meetings with a lack of follow-up was a big issue.

Giles said he felt the biggest lesson learned from the South Branch project was that revealed a lack of public contact or consultation and urged council to take responsibility for “access, transparency, honesty, respect for all voices, and courage to change position and challenge authority, if it is the right thing to do.”

Mayor Steven Byvelds** responded with “I think we are an open council. We do not have informal meetings and do not discuss council issues away from the council table.” ***

 

*They are not “farms”

**Remember that name, especially in the next municipal election, October 2014

***Because that would be ILLEGAL under the Municipal Act, wouldn’t it?

Aerial photo of South Branch wind power plant by Ralph Butler

Prowind sells South Branch/E Ontario project to US wind giant EDP

25 Thursday Oct 2012

Posted by ottawawindconcerns in Health, Wind power

≈ 1 Comment

Tags

Brinston, Chris Bentley, cost of electricity Ontario, Dwight Duncan, EDP, Prowind, Shanly, South Branch, South Branch Wind Opposition group, South Dundas, Tim Hudak, wind power

From this week’s Chesterville Record, news that Prowind sold its 14-turbine project to Houston-based EDP.

See the story here:

http://chestervillerecord.com/2012/10/wind-farm-pursued-in-n-stormont/

This is bad news for the community there–Prowind already has a Feed In Tariff or FIT contract for the project. Now, as owner, EDP will simply be able to add to it without additional environmental assessments or any other sort of oversight.

Not that there is any, anyway.

The subsidies given to wind power developers under FIT amount to about $500,000 per turbine, per year. Just a few kilometers away from Cornwall, which purchases cheap hydro power from Quebec for about 6 cents a kWh, the South Branch project will have a nameplate capacity of 30 megawatts. This is power that Ontario does NOT need.

In other news, in Ottawa at a Town Hall last evening, PC Leader Tim Hudak repeated his pledge to cancel the Feed In Tariff program if his party wins the next election.

Energy Minister Chris Bentley announced today that he is not seeking the Party leadership and is indeed leaving politics. Asked in Ottawa if he was surprised that Finance Minister Dwight Duncan was leaving politics, Mr Hudak said, “Who can blame him? Six budgets and he never once balanced the budget and now he’s leaving behind the worst financial mess.”

Email us at ottawawindconcerns@yahoo.ca and join our community of families concerned about the impacts of large-scale wind power generation projects on our communities, our health, the environment, and our economy.

For more news of our colleague group in South Dundas, go to http://www.stopbigwind.ca

Member: Wind Concerns Ontario http://www.windconcernsontario.ca

Newer posts →

Recent Posts

  • Turbines go up, turbines come down
  • Ontario electricity file “absolute disaster”: Premier Ford
  • Construction in full swing at Nation Rise
  • Return of land-use planning for renewable energy means action needed now, Ottawa committee told
  • Wind power lobby hopes Ontario forgets all the bad stuff about wind turbines

Follow me on Twitter

My Tweets

Enter your email address to follow this blog and receive notifications of new posts by email.

Tags

Bob Chiarelli electricity bills Ontario Green Energy Act IESO Ontario Parker Gallant wind farm wind farms wind power wind turbines

Contact us

PO Box 3 North Gower ON K0A 2T0

Create a free website or blog at WordPress.com.

Cancel
Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy