Amherst Island community tearing apart: “No way would anything this tall with this opposition be built in the city”

Tags

, , , , , , , , , , ,

Amherst Island is a small community offshore from Kingston, Ontario, which if Toronto-based wind power developer Algonquin Power gets its way, will soon be populated by as many as 37 huge wind turbines.

The community has been ripped apart by the controversy, as is becoming typical for rural Ontario communities where farm owners want the revenue from leasing their land for the turbines, while other residents worry about health and property values.

Here is a feature article from this week’s Farmer’s Forum, by Patrick Meagher. http://www.farmersforum.com/DEC2012/p12.htm

 

The big chill

Eastern Ontario’s latest battle over wind turbines reveals another divided community

 

By Patrick Meagher

 

AMHERST ISLAND — Bruce Caughey is the only dairy farmer on the 20-kilometre long Amherst Island, a three-kilometre offshore ferry ride west of Kingston. In 1970, there were 28.

Times have changed. Looks like they’re changing again.

If Algonquin Power & Utilities Corp. has its way, there will be 33 to 37 new wind turbines, each standing 50 storeys tall, on the humble island. Contracts have been signed, so Caughey expects to see eight of them from his back window.

“This is not a popular project,” he said, noting that the year-round population of about 410 people (2011 census) are overwhelmingly against it. Some say the issue has defined people by who now waves to whom.

“You can have differences of opinion,” Caughey said. “Most people rise above that. There are lots of social things we still enjoy together. Most people get along.”

Amherst Island is the typical story of many small Ontario communities where ugly battles have erupted over a landowner’s right to do what he wants on his property versus the neighbour’s right to the enjoyment of his property.

Despite worry about killing birds, the biggest issues are health concerns caused by the turbines and having to look at them. You can see the turbines towering over neighbouring Wolfe Island from the grassy southeast. To some they look good. To others they don’t. To some who lease land for a turbine, they look like money, up to $15,000 per year. Others cynically said the island will become a factory. The ones on Amherst will be taller by 20 to 30 metres, reaching 150 metres from ground to the tip of a vertical blade.

Caughey visited a farmer with three turbines on Wolfe Island and was struck by the “haunting” afternoon shadow but also the noise. The farmer told him they can sometimes sound like a jet plane taking off. A neighbour and a visiting veterinarian said they have heard it too.

“The only people getting a return are the landowners but we’re all going to enjoy them or not,” said Caughey, who once considered signing up for a turbine.

The setback is 550 metres but Caughey agreed with others that setbacks from homes should be at least one kilometre.

Local councilor for Loyalist Township, Duncan Ashley, lives on the island and said that in 18 years in municipal politics this issue is by far the most divisive. “Without a doubt,” he said. “Nothing comes close. This is tearing the community apart.”

Farmers Forum conducted a survey of 200 of Wolfe Island’s residents last year and the most significant conclusion was that 28.5 per cent of respondents said that community spirit had gotten worse since 86 turbines were erected in 2009.

Even though Premier Dalton McGuinty announced a priority points system that sends projects that are not community-supported to the bottom of the list, Ashley said he has not seen any legislation that gives municipalities power to stop a project. “Municipality rights have been stripped,” he said.

Some road work has been done to bring in the wind turbines and the province is considering a multi-million dollar upgrade of the ferry but the wind project has yet to be approved.

The president of the Association for the Protection of Amherst Island, Peter Large, said that 15 to 18 landowners have signed a deal to get a wind turbine but 200 people have signed on with the association in protest, representing the “vast majority” of the year-round adult population.

Large makes numerous arguments but there are two that stand out: health concerns and lack of local autonomy.

There’s no way that a building this tall would be approved in a city with such overwhelming opposition from the community, he said, adding that there is no local input, no hearing and no appeal process. “This in itself is unthinkable.”

The many health concerns from existing wind projects are now being studied by Health Canada, which expects to reach conclusions in about two years.

One concern, which has rarely been discussed in the news media, is the shadow flicker or strobe light effect created by the setting sun passing behind the turning blades and casting long but interrupted shadows into homes. (Google “wind turbine shadow flicker” and see the shadow action for yourself.)

Loyalist Township planner Murray Beckel said that if the project is approved he suspects turbine construction will not start until 2014, as the company first needs to hold a second open house in the new year and then provide numerous reports to the Ministry of Environment and obtain various permits. The ministry will need about six months to respond to the report package, he said.

But while the opposition has the numbers this is far from a one-sided battle. The pro-wind group has the law on its side. It also has long-time residents, mostly farming families, said sheep farmer Dave Willard, who stands to gain from two wind turbines on his property. “Every traditional island family that has been here for three, four, five generations are all on side but one (dairy farmer Bruce Caughy),” he said. “I can’t think of one other long-term island family that is opposed. Almost everyone with 100 acres signed on.”

He added that some families signed on but didn’t get a turbine and will still earn $2,500 a year for the 20-year term of the project.

“I don’t like being dictated to by a group of newcomers (fewer than 30 years),” Willard protested. “They don’t have historical authority. They didn’t raise their kids here.”

Editor’s note: APAI is a sister organization to Ottawa Wind Concerns, as group members of Wind Concerns Ontario. http://www.windconcernsontario.ca

How “green” is this?

Tags

, , , , , , , , ,

Perhaps you are aware of the 60-megawatt wind power project proposed for Manitoulin Island. Northland Power recently got its approval and the latest development is that the citizens’ group there, Manitoulin Coalition for Safe Energy Alternatives or MCSEA, has withdrawn its application for an appeal. “The deck is stacked against us,” said leader Raymond Beaudry. He pointed to the dismissal of an appeal of the huge Samsung project in Chatham-Kent, saying that the “test” to prove irreversible harm to the environment was impossible.

Construction on the Manitoulin project is underway right now, with mature trees being felled like matchsticks to make way for the huge access roads needed to build and maintain the project.

This first phase is 60 MW or about 24 turbines but plans mean the island–known to native peoples as Great Spirit Island–could eventually have 600 turbines.

Here is a photo of the destruction going on this week. This type of impact on the environment is irreversible. In 20 years, when the whole wind “scam” will be over, and the profiteers long gone, the damage will live on.

Email us at ottawawindconcerns@yahoo.ca and donate, Please! to PO Box 3, North Gower ON K0A 2T0

Please look for news daily at http://www.windconcernsontario.ca

ManitoulinTreeRemoval

Electricity technologist details turbine woes

Tags

, , , , , , , , , , ,

About 50 people gathered in the Mountain Agricultural Hall in South Mountain yesterday (what a pretty village!) to hear David Colling, former dairy farmer now feed supplier from the Ripley area.

Mr Colling explained that he now measures electricity “pollution” in homes and on farms, and has done more than 500 farms over the last five years. he was visiting three clients in the Eastern Ontario area.

When a Ripley area family came to him several years ago with concerns about the wind power project near them, he said he didn’t believe there could be a problem, but he went out and measured the electricity anyway. His advice: Get out of this house, now. The electricity pollution was so bad, he said it would have destroyed a herd of dairy cattle within six months.

Several families became ill after a wind power project started in the Kincardine area: the source of their problems seemed to be not just the turbines themselves but the substation* that was located across the road from them. Two of the families have now abandoned their homes, while the third family remains–they can’t afford to leave their home behind.

“The government of Ontario only cares about the big corporations producing wind power,” he concludes after speaking with people who have to live near wind power projects all over the province. “They clearly don’t care about you and me.”

One interesting fact about the turbine projects is that earthworms disappear in the area. Sonic vibration and electricity force the earthworms to leave, farmers tell him; the impact zone is a stunning FIFTEEN ACRES.

For more information go to his website HERE: http://www.electricalpollution.com/windturbines.html

Prepare to be stunned by what you read.

You can email us at ottawawindconcerns@yahoo.ca and please, donate to help us with the cost of legal advice. When the Feed In Tariff subsidy program opens again, Prowind will be in a position to re-apply. We’re going to need to step up our activities to protect this community.

PO Box 3, North Gower ON  K0A 2T0

*The substation for the proposed North Gower-Richmond wind power project is to be located just west of Fourth Line Road.

Ottawa Wind Concerns chair awarded Jubilee medal

Tags

, , , , , , , , , ,

Member of Parliament for Nepean-Carleton Pierre Poilievre gave Queen Elizabeth II Diamond Jubilee Medals to four community members  last evening. The MP said that too often, politics and media concentrate on urban life when he said, the rural communities are in many ways the backbone of Canada.

One of the awards went to Ottawa Wind Concerns chair Jane Wilson, who is also the president of Wind Concerns Ontario.

Mr Poilievre said in specific that the award was to acknowledge advocacy work to protect the health and safety of people living near industrial-scale wind power projects.

Several months ago, Mr Poilievre launched a petition to be taken to the House of Commons to ask for a halt to the Ottawa wind power project based in North Gower-Richmond, to wait until the results of health impact studies are available. (The petition is still availble for signing–contact us, or drop into the MP’s office at 250 Greenbank.)

He also commissioned an economic review of the project by the Library of Parliament, which found that the cost to taxpayers in Ontario for the power project would be $4.8 million, per year.

We are going to fight ON. And ON. It is not fair that an entire community should be affected by the decision of a few landowners to put profits before their community.

To donate–we need funds for ongoing legal advice–please send a cheque to PO Box 3 North Gower ON   K0A 2T0. To have your name added to our (confidential) email list, email us at ottawawindconcerns@yahoo.ca

North Dundas votes NO to turbines

Tags

, , , , , , ,

Just a few minutes south of the Ottawa area, the community of North Dundas is facing a wind power development proposed by Germany-based Prowind…which has now been sold to U.S. wind power developer EDP.

A motion was brought before North Dundas council this week…and the council voted AGAINST municipal support of the wind power project.

“This was a resounding NO,” says resident Theresa Bergeron.

The vote was unanimous.

Final recorded vote will take place November 13.
Email us at ottawawindconcerns@yahoo.ca

Donations may be sent to PO Box 3, North Gower ON K0A 2T0

NEXT DATE: November 25 in North Dundas, Ripley area farmer and farm electricity expert Dave Colling travels to Eastern Ontario to talk about experiences with farming and wind power projects.

 

Prowind sells South Branch/E Ontario project to US wind giant EDP

Tags

, , , , , , , , , , ,

From this week’s Chesterville Record, news that Prowind sold its 14-turbine project to Houston-based EDP.

See the story here:

http://chestervillerecord.com/2012/10/wind-farm-pursued-in-n-stormont/

This is bad news for the community there–Prowind already has a Feed In Tariff or FIT contract for the project. Now, as owner, EDP will simply be able to add to it without additional environmental assessments or any other sort of oversight.

Not that there is any, anyway.

The subsidies given to wind power developers under FIT amount to about $500,000 per turbine, per year. Just a few kilometers away from Cornwall, which purchases cheap hydro power from Quebec for about 6 cents a kWh, the South Branch project will have a nameplate capacity of 30 megawatts. This is power that Ontario does NOT need.

In other news, in Ottawa at a Town Hall last evening, PC Leader Tim Hudak repeated his pledge to cancel the Feed In Tariff program if his party wins the next election.

Energy Minister Chris Bentley announced today that he is not seeking the Party leadership and is indeed leaving politics. Asked in Ottawa if he was surprised that Finance Minister Dwight Duncan was leaving politics, Mr Hudak said, “Who can blame him? Six budgets and he never once balanced the budget and now he’s leaving behind the worst financial mess.”

Email us at ottawawindconcerns@yahoo.ca and join our community of families concerned about the impacts of large-scale wind power generation projects on our communities, our health, the environment, and our economy.

For more news of our colleague group in South Dundas, go to http://www.stopbigwind.ca

Member: Wind Concerns Ontario http://www.windconcernsontario.ca

Cancelled gas plants: what’s another 20,000 pages?

Tags

, , , , , , , , , , , ,

The big news out of Queen’s Park today is that while the Liberals thought they had complied with The Speaker’s request for documents pertaining to the Oakville and Mississauga gas plant cancellations (if you can call hundreds of blank pages complying with anything), there appears to have been an Oops!

Turns out now, the Ontario Power Authority (OPA) has discovered 20,000 more pages of documents connected to the cancellations.

In a nutshell, the Liberal government cancelled the plants because the people in Oakville and Mississauga–who NEED the power–didn’t want them, and an election was coming. So, now the government has decided to move them, guess where, rural locations, and then build the capacity it needs in the form of new transmission lines, new gas lines, whatever, so the resource hinterland of rural Ontario can feed Toronto.

How much is this costing you? Plenty.

Here is a summary from Ottawa Wind Concerns friend Robert Lyman, a former director in the federal government who was involved in energy policy.

ONTARIO ELECTRICITY RATEPAYERS – PAYING FOR POLITICS

Over the past year, there have been a series of announcements by Brad Duguid, Ontario Minister of Energy and his successor, Chris Bentley, about the construction of electricity generation projects in the province. Those announcements have all been related closely to the October 7, 2011 provincial election, which the Liberals won with a minority. Unfortunately, few citizens have understood the implications of the announcements.

This may have changed due to the work of two experts: Parker Gallant, a retired banker who has devoted several years to monitoring and reporting on the financial performance of Ontario’s electrical energy Crown Corporations and Bruce Sharp, an electrical engineer. You can read their excellent analyses in the online version of the Financial Post (“Ontario’ Power Trip: The $733 million gas boondoggle” by Bruce Sharp, and “Atikokan Conversion – Another Seat Saver for the Liberals!” by Parker Gallant). Their analyses are obscured, however, by the complexity of the subject matter. I will attempt to make it clearer.

Atikokan

In the period leading up to the 2011 provincial election, there were a number of announcements concerning electrical energy generation in the Atikokan area:

  • On September 11, 2011, Brad Duguid announced that the existing 200 MW Atikokan coal plant would be convert to biomass. Subsequent announcements promised that the contractor, Aecon, would complete the conversion for $170 million and that there would be 200 construction jobs for two years.
  • Chris Bentley subsequently announced that the Ontario Power Authority had contracted for the supply of 200 MW of electrical energy from wind turbines and solar generation.

These announcements were well received by the residents of Atikokan. In the 2011 election, MPP Bill Mauro of Thunder Bay Atikokan beat out the NDP candidate by 39% to 37%; this was less than 500 votes.

 

Subsequent analysis by Parker Gallant revealed some interesting things:

  • The contractor, Aecon, has contributed more than $45,000 to the Liberal Party of Ontario over the past four years and the Liberal Government has appointed the Aecon CEO to the Board of Directors of the Ontario Power Authority since its creation.
  • Over the last two years, the Atikokan coal plant has produced power at 2.6% of its capacity, which means that it has not been needed to support Ontario’s demands.
  • The conversion of the Atikokan plant to biomass (which would use wood chips as fuel) would actually reduce its ability to produce power from 175,000 to 140,000 megawatt hours.
  • As wind and solar energy plants produce electricity on an intermittent basis (i.e. when the wind blows and the sun shines), they are not sufficiently reliable to serve the needs of the pulp and paper plants in the area. This will require the construction of an east/west transmission line at a cost of $600 million to ensure reliability of energy supply to the region.
  • Considering the cost of the coal plant conversion, of the subsidies to the wind and solar plants and of the east-west transmission line, the total expenditures in this area will be close to $1 billion.

Oakville

Prior to the 2011 election, there was considerable controversy over the proposal by TransCanada Energy Corp., under contract to the Ontario Power Authority (OPA), to build a 900-megawatt natural gas-fired generating station near Oakville. The Ontario Cabinet decided, in the face of the controversy, to breach the $1.2 billion contract with TransCanada and to build the plant instead in Lennox, Ontario on land held by the government-owned Ontario Power Generation (OPG).

On September 24, 2012, Chris Bentley announced that a settlement had been reached between OPA and TransCanada over the breach of contract. The announcement focused on two payments to TransCanada – $40 million to cover sunk costs and a $210 million “turbine payment”, which was not explained.

The details that have emerged subsequently are as follows:

  • The turbine payment is an elaborate shell game. OPA has agreed to pay TransCanada $210 million for two gas turbines at the new plant. By 2017, when the new plant is completed, OPA will be sitting on a $210 million liability. When the plant starts producing electricity, TransCanada will repay the $210 million over the 20-year term of the contract, using revenues received from Ontario ratepayers. Under Ontario’s green-energy plan, even if the Lennox plant’s power is not needed, electricity ratepayers will still pay for the electricity they don’t need.
  • It is likely that the plant will not be needed. It will be located right next to an existing OPG plant that is seldom needed. When that plant does operate, it sells electricity into the export market below cost.
  • The turbine payment was far too high. If the plant had been located at Oakville, TransCanada would have been fully compensated for its costs with a payment of $113 million, $97 million less than the government has agreed to pay.
  • The gas services costs for the Lennox site, further away from the natural gas hub, may be higher than anticipated. Bruce Sharp estimates that they will be $346 million over the 20-year project term.
  • Locating the power plant farther away from the GTA will require up to $250 million in additional transmission facilities.
  • The total estimated cost of moving the project from Oakville to Lennox may thus be $733 million. This does not include other, to-be-determined costs, such as the compensation that will have to be paid to Ontario Power Generation for its land at Lennox. The figures contrast sharply with the $40 million the Ontario government has been citing.

Mississauga

The Atikokan and Oakville plants are in addition to the $190 million that the Ontario government had to pay to cancel a plant that would have been built in Mississauga. Similar to the Oakville decision, the cancellation of the Mississauga plant, made two weeks before the election, was followed by a decision to build the needed gas plant in Lambton, near Sarnia, which will add significantly to the electricity transmission costs.

In May, 1997, the MacDonald Commission issued its report recommending that the Ontario government introduce more competition into Ontario’s electricity system, including privatization of Ontario Hydro. Fifteen years later, electricity remains a publicly-owned and managed political football in Ontario.  Consumers will continue to pay dearly until this is changed.

Email us at ottawawindconcerns@yahoo.ca

Donations welcome for legal advice etc PO Box 3 North Gower ON   K0A 2T0

(Our mailbox is courtesy of the generous donation from a community member—thank you!)

A word about our photo

Tags

, , , , , , , ,

The rather elegant photo of Ottawa in our header needs an explanation: if there were a wind turbine in it, of the scale being proposed for south Ottawa, it is so tall you wouldn’t be able to see the nacelle or hub of it …. that is exactly how big these machines are. And of course, what they look like isn’t the issue, it’s the noise and the vibration they produce.

But, we need people to understand the scale of these power generating machines. Now, imagine TEN of these machines in the background of our photo…or 20 or 40 or 60 or—as in the Enbridge project near Kincardine, 120, or as in what Samsung is doing in Haldimand-Norfolk and Chatham-Kent, FIVE HUNDRED turbines…and you get an idea of what we mean when we say wind power projects are industrializing the small communities of Ontario.

It is expropriation with compensation. It is sacrificing the quality of life in our communities, reducing property values and harming health…all for an ideology for which there is no evidence of benefits.

We repeat a comment from then sales rep for Prowind, headquartered in Germany, who is behind the project in Richmond-North Gower and South Dundas. When asked by Mark Sutcliffe whether the wind turbines make noise (Talk Ottawa, April 2010) he said, “Of course they do! They’re power plants!”

What we need is a safe reliable power source that does not sacrifice anyone’s health or quality of life.

Email us at ottawawindconcerns@yahoo.ca and please consider donating toward our legal and other costs. We accept PayPal or cheques at PO Box 3 North Gower On  K0A 2T0 Ottawa Wind Concerns is a corporate member of Wind Concerns Ontario http://www.windconcernsontario.ca

What kind of person…?

Tags

, , , , , , , , , , ,

We’re not sure who “Andy Braid” of Kars is, nor do we get why Mr Braid seems to have letters published with regularity in The Manotick Messenger (3 weeks in a row, by our count) but at least our response to his recent letter about the wind power project was published, yesterday.

Here is the letter.

Mr Braid claims that MP Pierre Poilievre hasn’t got his facts straight in asking for a moratorium on the proposed wind power project for our community. It is Mr. Braid who is in error.

Ontario uses coal power for less than three percent of its electricity needs, and could shut them off altogether for seven months of the year when they are not needed for spikes in demand due to hot weather. The truth is, Ontario’s pollution comes from cars and trucks, and from industry south of the border.

Most worrying, however, is his objection to Health Canada spending time studying the noise problem. What kind of person does not want more information on a public health issue, and is in fact willing to sacrifice the health of his neighbours in North Gower, Richmond and Manotick?

Wind power has not been proven to reduce greenhouse gases anywhere in the world.

Jane Wilson

Ottawa Wind Concerns

Mr Braid’s comments, it might also be noted, come right out of the wind power developers’ lobby group playbook. They don’t want Health Canada to study the turbine noise and infrasound. If the study is done right–and many are commenting on the current proposed study design (it has flaws) to improve it–it will show that there are questions about setbacks and nighttime noise.

Ontario could end up with 2-km setbacks (minimum in the view of the World Health organization and the Society for Wind Vigilance) and perhaps also having the turbines turned off at night, as they are now doing in some areas of France. That means less profit in the form of taxpayer subsidy for the big companies.

Email us at ottawawindconcerns@yahoo.ca and donate to PO Box 3, North Gower ON   K0A 2T0

Landowner with turbine lease: “I wouldn’t sign now”

Tags

, , , , , , , ,

One of the things we have heard from a number of communities is that landowners who signed options and then those options turned into leases for industrial-scale wind turbines, is that they wish they had learned more about the whole issue before they signed.

A lawyer told our community group, If landowners had had a lawyer read over some of those contracts, the advice would have been NOT to sign.

The reasons are several: you virtually give away all rights to your own land for 20 years and at the end of that time there is a first right of refusal. In the United States for example, the leases are written in such a way that they are really 60-year leases, not 20.

But what happens quickly is the community reaction when a landowner decides to put money first and sign on the dotted line. Neighbours of the leased property tend to object when they learn that their property values are going to plummet (this is true regardless of what the wind power industry claims), their community industrialized and, worst of all, they are at risk of being made ill by the environmental noise and infrasound.

Here is an account of one farm owner’s statements from the dairy-rich Listowel area of Ontario. Note that the farm-owner now believes he was misled by the wind power developer (Invenergy in this case).

A link to the full story follows.

Doug Hoshel, the Britton landowner who leased the three turbines in question, said his feelings towards wind turbines have certainly changed since he signed the contract with Invenergy last October.

“I would never sign one now, mainly because of what it’s done to the community,” Hoshel said. “There’s so many unanswered questions I wasn’t aware of when I signed.”

 The draft site plan also conflicts with Hoshel’s understanding of the project, which was described by Invenergy Canada as a low-density project with one turbine every 100 acres and no more than three turbines per rural block. The draft site plan now shows Hoshel with three turbines on his 100 acres farm, leaving him feeling like he was misled.

 “The last thing I want is for someone to get sick because of something that’s on my property,” Hoshel said. “I love this community, and I’m concerned about it.”

http://www.southwesternontario.ca/uncategorized/welfare-of-children-at-risk-due-to-wind-turbines-parents-say/

****PLEASE be sure to sign the petition put forward by Nepean-Carleton MP Pierre Poilievre, asking the Ontario government not to approve the North Gower-Richmond area of Ottawa wind power project, while the Health Canada study is ongoing. A copy of it is on this website under documents, or you can go to Mr Poilievre’s office at 250B Greenbank Rd and sign there.