Tags
Brinston, EDP Renewables, electricity supply Ontario, environmental assessment, green energy, MInistry of the Environment and Climate Change, MOECC, Morrison Hershfield, Nation Rise wind farm, North Stormont Ontario, renewables, South Branch wind farm, wind farm, wind power
Power developer project documents are missing key details, engineering firm tells Municipality of North Stormont

Concerned Citizens of North Stormont leader Margaret Benke, in Finch, Ontario: MOECC has poor track record in meeting its responsibilities
August 9, 2017
Last week, Portugal-based EDP Renewables filed documents with the Ministry of the Environment and Climate Change (MOECC) as part of the Renewable Energy Approval (REA) process, to get final approval for its “Nation Rise” wind power project in North Stormont, just south of Ottawa.
Using every tool they have to act responsibly on behalf of citizens, North Stormont had engaged Ottawa engineering firm Morrison Hershfield to conduct a review of the documents presented earlier.
The firm found that key information was missing from the project documents in critical areas such as the impact of the project on groundwater, and on bird and bat populations, to name two. An excerpt from the Morrison Hershfield report, tabled at a late June Council meeting, follows.
- No review has been completed for potential impacts of the project on potable water sources. While potential impacts to groundwater resources have been reviewed from a biophysical perspective, no review has been completed to assess the potential impacts to groundwater resources from a potable water quantity and quality perspective.
• No review has been completed for potential impacts of the project on prime agricultural lands (Class 1-3 agricultural soils)
• Confirmation letter from the Ministry of Tourism, Culture and Sport regarding completeness of archaeological and cultural heritage assessments has not been received for the project as described in clauses 22 (a) and 23 (3) (a) of Ontario Regulation 359/09;
• Confirmation letter from the Ministry of Natural Resources and Forestry regarding completeness of natural heritage assessment and birds and bats EEMP has not been received for the project as described in clauses 28 (3) (b) and (c) of Ontario Regulation 359/09;
• Significant details are missing on the project description (e.g. location and type of permanent meteorological towers & location of the 2-3 proposed staging areas of 2-7 hectares each); and
• No detailed review has been completed to assess potential effects of the project construction on municipal infrastructure.
The consulting firm recommended to Council that North Stormont ask for these reports to be provided, including an assessment of impact on groundwater and municipal infrastructure such as roads.
Read the engineering firm report here.
There is no information on whether EDP complied with the request from North Stormont before filing project documents to be screened for “completeness” by the MOECC.
Citizens in the area are very concerned about the power project. Margaret Benke, a leader with Concerned Citizens of North Stormont, told Ottawa Wind Concerns “You can imagine that with 825 homes within 2km of one and up to 10 proposed turbines, and both Crysler and Finch villages within 3km of multiple turbines, we are bracing for the worst.
The group is especially concerned following release of a report by Wind Concerns Ontario in June, showing that the MOECC has failed to respond to thousands of reports of excessive noise from wind turbines.
“We have many apprehensive citizens,” Benke said. “Unless the MOECC changes its approach, we expect that we could be treated with the same lack of respect and consideration as the 3,200 other residents of Ontario who were largely ignored. We will continue our fight to protect our rural citizens, who deserve equal respect as citizens.”
EDP also operates the South Branch wind power project in Brinston; it took over a year to file its required acoustic audit to demonstrate compliance with provincial noise regulations for wind turbines, but there is no report posted on the company’s website.
The Nation Rise project will be 100-megawatt capacity using 30-35 industrial-scale wind turbines; Ontario currently has a surplus of electrical power and is regularly selling off extra at below-market prices, and paying wind power generators not to produce in times of low demand and high supply.
A report published by the Council for Safe a& Reliable Energy noted that 70 percent of Ontario’s wind power is wasted. (Ontario’s High-Cost Millstone, June, 2017)
Make sure that all of the residents whose homes will be affected read this warning from Dr. Marian Alves-Pereira. People in communities where projects could not be stopped are now dealing with the harm and it is serious.
http://ulsterherald.com/2017/07/30/expert-warns-adverse-health-effects-turbines/
Specifically, Dr. Marian Alves-Pereira says, “The illnesses that can be contracted from low frequency noise can include cardio vascular disease, it can affect your immune system, and some of the worst effects is late -onset epilepsy. The neurological damage can lead to psychiatric concerns and suicide.”
Who on the face of this earth would want to take the risk of having this happen to themselves or a member of their family? Who would willingly choose to submit to this threat of harm?The wind industry does not ask residents to sign a legal document wherein people give informed consent. In fact this information regarding harm is denied by our government agents and by the wind industry personnel.
Also check out the long list of wind turbine syndrome symptoms published on the Waubra Foundation website. These symptoms are early warning signs and the list details the cumulative impact over time. Once people start experiencing the initial symptoms, after the projects are turned on, they have no recourse with the MOECC or the MOH in Ontario.The turbines just keep running and the damage continues.
This is why the opposition in Ontario is so relentless and is finally getting media coverage.
Forced relocation of rural residents is not acceptable!
http://globalnews.ca/news/3490234/ontario-wind-turbines-family-complaints/
This story ran just weeks before Minister Glen Murray ‘quit’.
Pingback: Wind power developer documents found lacking: engineers’ report | ajmarciniak