• About
  • Donate!
  • EVENTS
  • Ottawa’s “Energy Evolution”: wind turbines coming to rural communities
  • Thinking of signing a wind turbine lease?
  • Wind Concerns Ontario
  • Wind turbines: what you need to know

Ottawa Wind Concerns

~ A safe environment for everyone

Ottawa Wind Concerns

Author Archives: Ottawa Wind Concerns

Algoma residents consider action on wind power plant approval

13 Sunday Oct 2013

Posted by Ottawa Wind Concerns in Health, Renewable energy, Wind power

≈ 1 Comment

Tags

cost-benefit analysis wind power, environmental damage wind power, Goulais Bay, Group of Seven Algoma, wind farm Algoma, wind power

The Goulais Bay wind power generation plant was approved October 4th, despite objections from all over Canada about placing an industrial power generation project in the landscape celebrated by Canada’s Group of Seven painters.

From SooToday:

Goulais wind farm approved, opponents consider next steps

Saturday, October 12, 2013   by: Darren Taylor

 

The Save Ontario’s Algoma Region (SOAR) group is clearly disappointed with the Ontario Ministry of the Environment (MOE) October 4, 2013 decision to approve construction of the Goulais Wind Farm project.

A Renewable Energy Approval (REA) has been given to SP Development Limited Partnership to build, install, operate and eventually retire a renewable energy facility, consisting of 11 wind turbines , with a total capacity of 25 MW, in the unorganized Townships of Pennefather and Aweres.

The wind facility will be connected to Great Lakes Power’s distribution system.

The REA comes with a long list of conditions, which include requiring SP Development Limited to construct and install the facility within three years of the date of approval, compliance with the MOE’s noise emission limits,  keep an eye on storm water management, sediment and erosion during and after construction, the effect of the project on wildlife (such as birds and bats), establish a community liaison committee with members of the public, and properly decommissioning of the facility upon its retirement.

SOAR’s Executive Member and spokesperson Gillan Richards, in an e-mail to SooToday.com, stated: “SOAR and Wind Concerns Ontario (WCO) will now consider what action to take in response to the Goulais Project Approval.”

The group, if it decides to file an application to appeal the MOE’s Goulais Wind Farm project approval, must do so within 15 days.

SOAR has long been opposed to the project, and has maintained that the whirring of wind turbines, for example, is detrimental to human health, and that the presence of more wind farms in Algoma would be an all-round disruption to the environment and wildlife in the area.

Also ranking high among the group’s concerns is that, in its view, the project will create an eyesore on the area’s famous Group of Seven landscape, disturbing “the natural beauty of Algoma from industrial intrusion.”

SOAR states the public in general has never been keen on wind turbine developments, claiming  “Algoma residents and visitors are already annoyed and dismayed by the intrusion of the Prince Wind Farm turbines.”

SOAR has also long insisted not enough public input has been gathered from the province and the developer regarding the Goulais Wind Farm project (along with other wind projects, proposed by other developers, for the Algoma region).

The group agrees with criticism from The Fraser Institute (a Canadian think tank based in Vancouver) that forecasts Ontario’s energy prices will increase dramatically (40 to 50 percent) in coming years, putting the blame for that on the use of wind and solar farms, and insisting that wind turbines are simply inefficient in producing electricity.

SOAR agrees with critics who state Ontario could have gone with cheaper alternatives, such as natural gas or nuclear power, when it sought to move away from coal-fired plants and brought in the Green Energy Act in 2009.

The Ontario government has said the Green Energy Act, despite higher costs for electricity, will ensure “cleaner” electricity for future generations.

Rex Murphy on “duplicitous Dalton”

13 Sunday Oct 2013

Posted by Ottawa Wind Concerns in Ottawa, Renewable energy, Wind power

≈ 2 Comments

Tags

Dalton McGuinty, gas plant cancellation scandal, national Post, Ontario energy policy, Rex Murphy

From the weekend edition of The National Post, Rex Murphy‘s summary of Duplicitous Dalton and the havoc wreaked up Ontario taxpayers. Who pays for all this “venality” Murphy asks: “the honest pockets of carpenters in North bay and teaching assistants and snow plow operators and store clerks and seniors…”
The horrible truth is, Ontarians are continuing to pay for the disastrous McGuinty energy policies as approvals of giant wind power projects continues, and subsidies are doled out by the million each week.

Wonder how Ottawa South voters are feeling about John Fraser this week…

Rex Murphy: Duplicitous Dalton, Inc.

Rex Murphy | 12/10/13 | Last Updated: 11/10/13 1:58 PM ET
More from Rex Murphy
Where is McGuinty now that the full cost of his expediency is known? Harvard, of course, disappeared like a member of some witness protection program for the well-connected.

Peter J. Thompson/National Post Where is McGuinty now that the full cost of his expediency is known? Harvard, of course, disappeared like a member of some witness protection program for the well-connected.
 

The Auditor-General of Ontario has released her report on the provincial Liberal government’s brazenly political decision to cancel two gas-fired power plants. Her estimate of the ultimate cost: about $1.1-billion, potentially reaching $1.5-billion. This obscenity of mismanagement and prevarication came out of Duplicitous Dalton, Inc., a.k.a. the McGuinty government, an administration we now know was, politically, so venal as to toss perhaps as much as a billion and a half taxpayer dollars into the devouring — but politically favourable — wind.

Kelly McParland: Here lies the wreckage of Dalton McGuinty’s self-serving gas plant decisions

In contemplating the disastrous consequences of the Ontario government’s two arbitrary gas plant closures, it does well to remember the performance put on by then-premier Dalton McGuinty before his abrupt resignation.
Never hesitant to play the Boy Scout, the premier prorogued the legislature rather than face questions about the gas plants, and then piously sought to blame the opposition for his troubles.
“I prorogued because the place was becoming overheated,” Mr. McGuinty insisted, citing a “spurious, phoney” suggestion that his energy minister had been in contempt of the legislature for failing to produce documents related to the scandal.

D.D., Inc. even had the brass to insist, originally, that the cost to cancel just the Oakville, Ont., plant was only $40-million. The Auditor-General this week, after a cautionary distribution of Gravol tablets to the assembled press, offered a more altitudinous range of $675-million to $810-million — 15 to 20 times as much! And from the very beginning of the noxious affair, to any question the Liberal response was delay, obfuscate, stone-wall, delete emails, deny said deletions, miraculously locate the not-so-deleted emails, and, of course, insult and hector any and all critics.
Let there be no more “used car salesmen” jokes about political leaders. Used car salesmen are pillars of candour and conscience compared to this lot.
They knew $40-million was a joke estimate from the moment they scrambled to “buy” the votes by scrapping the plant — in other words, from the moment they chose to buy a couple of ridings by ripping up contracts, costs be damned.

Read the whole article here.

Highlights from St Columban ERT: infrasound is real (we knew that)

10 Thursday Oct 2013

Posted by Ottawa Wind Concerns in Uncategorized

≈ Leave a comment

Ottawa Wind Concerns's avatarWIND CONCERNS ONTARIO: On WordPress

Dr. David Michaud at the St. Columban ERT Hearing

“Knowledge gaps on noise, infrasound”

 

In testimony before the ERT Hearing on the St. Columban Project last week, Dr. David Michaud, the Principal investigator for the Heath Canada study into wind turbine noise, appeared to contradict Sylvia Davis, a lawyer for the MOE who questioned the existence of low frequency noise generated by wind turbines at the Ostrander Point ERT.   

   Dr. Michaud testified that there was a ‘knowledge gap’ in respect to low frequency noise emitted by wind turbines.  International standard used to assess noise do not consider low frequency noise as they do not deal with sound 31.5Hz.

 

  Dr. Michaud also stated that the knowledge gaps relative to both audible and low frequency noise from wind turbines were sufficient to qualify for Health Canada funding. He stated that to receive funding, a project…

View original post 163 more words

Tom Adams on wind and solar: not working

10 Thursday Oct 2013

Posted by Ottawa Wind Concerns in Uncategorized

≈ Leave a comment

Ottawa Wind Concerns's avatarWIND CONCERNS ONTARIO: On WordPress

From today’s Financial Post, Tom Adams and Kathy Hamilton on the latest Big Ideas for renewable power in Ontario.

Ontario’s latest electricity scheme: Pumped energy storage

Tom Adams and Kathy Hamilton, Special to Financial Post | Published: 10/10/13 9:31 AM ET

For ratepayers, none of this is working. Wind and solar are not just unreliable. Ratepayers pay unaffordable prices for their chaotic output. Adding the cost of storage puts ratepayers in double jeopardy.
Daniel Acker/Bloomberg

As the Ontario government’s $1-billion gas plant relocation scandal slips into history, the province’s electricity ratepayers should not assume that the era of big-ticket rate-boosting power projects of questionable value is a thing of the past. Now comes the “Smart Grid” and a host of other projects.

Smart Grid is the new fad taking over power industry policy everywhere — it’s a flexible concept that gives utilities, contractors and governments room to justify ratepayer spending on “Smart Meters,” electric cars, power line automation and the new hot idea of electricity storage.

None of these ideas comes cheap, including pumped electricity storage, a plan making its way through…

View original post 211 more words

The Auditor General’s report on gas plants: a summary

09 Wednesday Oct 2013

Posted by Ottawa Wind Concerns in Ottawa

≈ 1 Comment

Tags

Bonnie Lyserk, cost of power Ontario, gas plant cancellations Ontario, Ontario's electricity system, power demand Ontario, Robert Lyman

Here from Ottawa economist Bob Lyman, who specializes in energy issues, is what you need to know about the Auditor General’s report, and why the losses mounted up to over $1 billion for both the Oakville and Mississauga gas plants.

ONTARIO AUDITOR GENERAL’S REPORT  ON OAKVILLE POWER PLANT CANCELLATION COSTS:  SUMMARY AND BRIEF COMMENTARY

Introduction

On October 8, 2013, Bonnie Lysyk, Auditor General of Ontario, released a Special Report on the costs that have been incurred and are likely to be incurred by the public as a result of the cancellation of a natural gas-fired electricity generation plant in Oakville Ontario. In the period leading up to a provincial election, the Liberal government announced the cancellation of this plant on October 7, 2010. As a result of the cancellation, the Ontario Power Authority (OPA) was required to negotiate arrangements for the construction of alternative power generation facilities in Napanee, Ontario. Thus, the objective of the Auditor General Office’s review was to determine the costs of both the cancellation of the Oakville plant and the relocation of the power generation facilities to Napanee.

Background

The need for a natural gas electricity generation plant in the Southwest Greater Toronto Area was first identified by the OPA in its 2007 Integrated Power System Plan. In response to the plan, the Minister of Energy and Infrastructure directed the OPA in 2008 to procure a combined–cycle natural gas generation facility in the area with a capacity of up to 850 megawatts (MWs), to begin operating no later than December 31, 2013.

In September, 2009, the OPA awarded a contract to TransCanada Energy Ltd. (TCE) to build the facility in Oakville. There followed significant local opposition from groups in the Oakville area, including the Town of Oakville. The government cancelled the project. Soon after, OPA and TCE began to negotiate a settlement on a replacement project. TCE had already incurred significant costs and was facing the loss of revenues it would have received if the original contract had been honoured. The negotiations were difficult. The Premier’s Office intervened, without consulting OPA, to assure TCE that it would be compensated for the financial value of its contract for the Oakville plant. The Minister of Energy instructed OPA to contract with TCE to build a new plant in Napanee. Finally, the Province and OPA agreed to an arbitration framework (for determining damages to be paid to TCE if no settlement was reached) that favoured TCE and waived the protections that OPA had under the original Oakville contract. In December, a deal was reached to relocate the plant to Napanee.

Cancellation Costs

 The Special Report lists two types of costs that resulted from the plant cancellation -the costs already incurred and the estimated future costs.

The costs already incurred include reimbursing TCE for its initial purchases of gas turbines for the Oakville plant and the modifications made to them ($210 million), sunk operating costs relating to the Oakville plant ($40 million) and legal fees ($3 million).

The estimated future costs essentially relate to the cost of constructing the Napanee plant, of increased gas connections to get natural gas to the Napanee plant, the costs of new gas pipelines to move gas to Napanee and new electricity lines to move electricity from Napanee to the GTA, the penalty associated with the use of less efficient gas turbines, and the cost of replacement power to make up for the non-availability of the Oakville plant’s power for some time. The Auditor General’s Office estimates these costs to be $859 million.

The total costs incurred plus estimated future costs are thus $1,112 million (i.e. $1.1 billion).

Estimated Future Savings

 In return for taking on a portion of the costs that TCE would have incurred, OPA was able to negotiate a lower price for the power from the Napanee plant than it would have had to pay for the power from the Oakville plant. This results in an expected savings of $275 million. There is also a delay in the commencement of payments to TCE compared to what would have occurred under the Oakville contract because the Napanee plant will come into operation later. The OPA and Auditor General disagree on both the dates when the Oakville plant would have come into operation and when the Napanee plant will come into production. As a result of these disagreements, the Auditor General estimates the present value of the savings to be $162 million, and OPA estimates it to be $539 million.

Using the Auditor General’s figures, the net cost to the public will be $675 million.

Impact of Potential Toll Increase

 TCE’s parent company will also benefit from the fact that under the Napanee agreement a section of the pipeline route owned by TransCanada Pipelines Limited (TCPL) effectively must be used to transport gas to Napanee. This section does not now have the capacity to transport the amount of gas that will be needed by the Napanee plant. Accordingly, TCPL will need to make additional capital investments and recover these costs through increased toll charges, which will get passed on to electricity ratepayers. Tolls could increase by up to 50% in the first three years; if so, over the 20-year term of the contract for the Napanee plant, the cost of gas delivery would increase by $140 million.

Special Observations

The Special Report makes some observations that raise concerns about the way the Ontario government managed this issue.

  • Throughout the initial procurement process for the Oakville plant, including prior to the awarding the contract to TCE in September 2009, OPA provided the government with “off ramps” not to proceed. Despite the public controversy and the firm opposition of the Town of Oakville, the government declined to take any of these off ramps.
  • The contract for the Oakville plant contained protection to relieve both TCE and OPA of any financial obligation if events beyond their control (force majeure events) caused the plant’s commercial operation date to be delayed by more than 24 months. Given Oakville’s strong opposition to the plant, including Oakville’s stated intention to fight the matter all the way to the Supreme Court of necessary, it may well have been possible for the OPA to wait it out, with no penalty and at no cost. In other words, if the Premier’s Office had not intervened to guarantee TCE compensation, there might have been no cost to the Crown.
  • The Minister of Energy agreed to locate the new plant in Napanee, hundreds of miles from the market for the power, and with no consideration of the potential opposition of people in Napanee.

I would also observe that the need for additional natural gas generating plants is closely linked with the Ontario government’s commitment to add significant additional generating capacity from “green” energy sources, mainly wind turbines and solar power equipment. These intermittent sources of power require much more conventional energy sources to back them up for periods when they produce little or no electricity.

In reality, Ontario already has significant surplus electrical generating capacity, a situation that seems likely to continue until 2018 at the earliest. The problem seems to be one that is entirely of the government’s own making.

Robert Lyman

Ottawa

Behind closed doors: who is really setting Ontario’s energy policies?

07 Monday Oct 2013

Posted by Ottawa Wind Concerns in Uncategorized

≈ Leave a comment

Ottawa Wind Concerns's avatarWIND CONCERNS ONTARIO: On WordPress

Parker Gallant: Who really sets Ontario’s Energy Policies?

(October 7, 2013)

In Ontario it’s a well-known fact that the Green Energy and Green Economy Act (GEA) was developed because a small group of people convinced a past Energy Minister, George Smitherman, it was needed. That group, the Green Energy Act Alliance (GEAA), even claim they helped him write the Act!

 

Several ministers later and things haven’t changed even though current Energy Minister, Bob Chiarelli has talked a lot about engaging communities, smaller municipalities and other stakeholders in revisions to the siting of gas, wind and solar generating plants. Minister Chiarelli has even invited input on revisions to the Long-Term Energy Plan (LTEP). Despite the rhetoric however, it still appears that the time spent by all but the environmental non-government organizations (ENGOs) will fall on deaf ears.

The writing was on the wall from the first announcement by Minister Chiarelli on…

View original post 1,325 more words

Parker Gallant: are Ontario’s electricity bills a regressive tax?

07 Monday Oct 2013

Posted by Ottawa Wind Concerns in Ottawa, Renewable energy, Wind power

≈ 1 Comment

Tags

cost benefit wind power, cost-benefit renewable power, Dalton McGuinty, Feed In Tariff Ontario, Kathleen Wynne, Ontario electricity bills, OPA, Parker Gallant

On September 10, 2013, when the temperature hit 34 degrees in Toronto, demand for electricity in Ontario peaked at 8 PM when we were consuming 22,417 megawatts (MW) of power.  At that point according to the Adequacy Report from the IESO, we still had excess capacity−8,437 MW in fact, or enough to power over seven million average Ontario homes.

So the question becomes, if we have power to spare, why do we continue to add expensive sources of power generation like wind and solar to the electricity grid?   Surely the addition of that expensive generation that must be backed up will do nothing more than drive electricity prices up.
Has our electricity system turned into nothing more than a form of wealth transfer or, perhaps, a regressive tax?   The latter is defined as: “A tax that takes a larger percentage from low-income people than from high-income people. A regressive tax is generally a tax that is applied uniformly. This means that it hits lower-income individuals harder.”
As it turns out, the management of our electricity system by the Liberal government during the past 10 years has been both.   Consider the following points and see if any of them were meant to keep our electricity prices competitive with other markets, and that might have helped to create jobs in Ontario. Job creation may have resulted in tax revenue that could have been use to reduce our deficit, improve health care, built better transit, or provide better government services.
Reality in Ontario today
Here is what ratepayers must accept:
§     Paying for smart meters and resulting time-of-use pricing–we eat supper after 7 PM and do our laundry in the middle of the night
§     Paying to replace smart meters because they “don’t communicate”
§     Paying for the development of the “smart grid” which turns out to be not so smart.
§     Subsidizing very large energy consumers by picking up a chunk ($200/400 million) of what they would have to pay if they were a household, just to keep remaining manufacturing jobs
§     Paying huge Net Revenue payments to gas plant electricity generators for sitting idle
§     Paying wind generators to not produce electricity
§     Paying solar generators to not produce electricity
§     Paying to erect meteorological stations to measure how much wind generators might have produced so that we can pay them for not producing
§     Paying for “steaming off” perfectly clean nuclear power from Bruce Power
§     Paying for the Ontario Power Authority to run ads on TV, radio and the newspapers to tell us to conserve electricity, racking up average annual spending of $300 million
§     Paying for costs of operating the Ontario Power Authority, which we were told was a temporary long-term planning agency
§     Paying to get the local distribution company to pick up old refrigerators and being told it’s free
§     Paying to move two gas generation plants at a cost of about $1 billion
§     Paying to have the school boards in Toronto and elsewhere put solar panels on their roofs so they could generate money to fix some of the roofs
§     Paying for grants to people that can afford to purchase new expensive electric vehicles (EVs)
§     Paying to put in charging stations for those EVs that use the streets but don’t pay gas taxes
§     Paying for someone else to use coupons to purchase CFL or LED light bulbs
§     Paying for grants to small and medium sized companies to retrofit their lighting systems
§     Paying for expensive electricity generated by solar panels placed on your local municipally owned arena
§     Paying for grants so your municipality can exchange incandescent and halogen street lights to LED lights
§     Paying your local distribution company extra money each year because their revenue deteriorated because you conserved electricity, so they asked for and got a rate increase blessed by the Ontario Energy Board
§     Paying to connect wind and solar generators to the transmission system run by Hydro One, a wholly owned provincial monopoly
§     Paying the cost of electricity produced by your neighbour for those solar panels on his roof for which he gets 80 cents a kilowatt hour
§     Paying for the costs of solar power produced by corporations like Loblaws, Canadian Tire,  IKEA, etc., which they sell into the electricity grid at 70 cents a kilowatt hour, but buy the power they need at the same (or lower) price that you pay
§     Paying forever for “residual stranded debt” that should have been paid off 5 years ago.
§     Paying for the sale of surplus electricity to New York, Michigan, etc. at a price 75/85% below its cost
§     Paying HST on our electricity bills which automatically added 7% to its cost and generates well in excess of $1 billion for the province’s coffers
Now look over these 28 points and think about which represent “wealth transfers” and which represent a “regressive tax.”   Review them again and pick out any that added cost-effective new generation.  Hint: you will probably have trouble finding the latter!
Ontario’s legacy
Energy Minister Chiarelli recently bragged about the reputed $35 billion in new investment attracted to the province by the Green Energy and Green Economy Act and the 31,000 jobs that it supposedly created. Those 31,000 jobs (most are relatively short term construction jobs) will cost the ratepayers of the province over $3 million each.
What Minister Chiarelli didn’t say was that the $35-billion investment will cost ratepayers well over $100/120 billion by the time those 20-year contracts have ended, and most of that will be extracted from the pockets of many Ontarians who cannot afford the “regressive tax” it has become. Many are discovering they can’t afford to turn their lights on for fear of being unable to buy groceries.
What a legacy for the McGuinty/Wynne team.
Parker Gallant,
October 3, 2013
The opinions expressed here are those of the author and not necessarily Wind Concerns Ontario.

Ontario communities to Wynne gov’t:STOP denying problems with wind power!

07 Monday Oct 2013

Posted by Ottawa Wind Concerns in Uncategorized

≈ Leave a comment

Ottawa Wind Concerns's avatarWIND CONCERNS ONTARIO: On WordPress

Coalition of ‘Unwilling Host’ Municipalities

Press Statement October 6, 2013

Over the past week, the total number of ‘Unwilling Host’ municipalities grew to 71 as South Dundas and Bruce County endorsed resolutions removing support for more wind turbines in their municipalities. This number has more than doubled since the provincial government announced in late May that they were going to address municipal concerns with the wind turbine program.  Two more Councils, Greater Napanee and West Elgin, are expected to consider related resolutions at meetings this week.

This growing opposition is a response to activities by wind turbine companies in areas not previously affected by projects and an understanding that Ontario does not need more electricity at this time.  Municipalities are seeing the impact of existing turbines on their communities or their neighbours and do not want the same things to happen in their municipality.  The government’s proposals for community benefit…

View original post 330 more words

Citizens of Prince Edward County fight on for the environment

07 Monday Oct 2013

Posted by Ottawa Wind Concerns in Uncategorized

≈ Leave a comment

Ottawa Wind Concerns's avatarWIND CONCERNS ONTARIO: On WordPress

Here, from The Wellington Times, is Rick Conroy’s update on the fight to save the environment at Ostrander Point in Prince Edward County.

 

Reloading

Gellespie-Standing

Eric Gillespie speaks to a gathering of the Prince Edward County Field Naturalists last week in Bloomfield.

PECFN readies for courtroom battle to defend Ostrander Point from MOE and developer

It was an evening to celebrate—to recognize a most improbable win against two powerful adversaries. It was also time to begin preparations for the next battle to save Ostrander Point from the development of industrial wind turbines.

The Prince Edward County Field Naturalists (PECFN) gathered last week at a hall in Bloomfield for a feast of homemade casseroles, salads and squares to rejoice in the Environmental Review Tribunal decision to revoke the approval of a nine industrial wind turbine project on Ostrander Point on south shore of Prince Edward County. The Tribunal ruled that…

View original post 1,052 more words

Greater Napanee says No

02 Wednesday Oct 2013

Posted by Ottawa Wind Concerns in Uncategorized

≈ Leave a comment

Ottawa Wind Concerns's avatarWIND CONCERNS ONTARIO: On WordPress

We reported yesterday that Gilead Power is actively prospecting for landowners to lease 10,000 hectares of land for a wind power project. The citizens of Greater Napanee held a public information meeting last night. Note the comments from a landowner who has been approached numerous times by the aggressive wind power developer.

Here is a report from local resident Bill Daverne.

Greater Napanee says “No”

Tuesday night, the Town of Greater Napanee held an open council meeting dedicated to public input on the proposed Gilead Power 40-80MW Dorland wind power project.

Dorland is to be sited in a 10,000-hectare swath of properties south and east of Hay Bay in the waterfront community in which Sir John A. Macdonald lived as a child, and which is today a mix of farms, residences and recreation properties.

Lease acquisition is well underway, but no Feed In Tariff or FIT contract has been…

View original post 618 more words

← Older posts
Newer posts →

Recent Posts

  • The stats tell the story: wind doesn’t work
  • Wind power locally: reliably unreliable
  • Has Ottawa lost its focus on city priorities?
  • Pro-wind groups in Ottawa collaborate to “educate”
  • Thinking of signing for a wind turbine lease? Better get informed to protect yourself

Follow me on Twitter

My Tweets

Enter your email address to follow this blog and receive notifications of new posts by email.

Tags

Bob Chiarelli Green Energy Act IESO Ontario Ottawa Ottawa wind concerns wind energy wind farm wind power wind turbines

Contact us

PO Box 3 North Gower ON K0A 2T0

Create a free website or blog at WordPress.com.

Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Subscribe Subscribed
    • Ottawa Wind Concerns
    • Join 377 other subscribers
    • Already have a WordPress.com account? Log in now.
    • Ottawa Wind Concerns
    • Subscribe Subscribed
    • Sign up
    • Log in
    • Report this content
    • View site in Reader
    • Manage subscriptions
    • Collapse this bar